VERIFICATION / VALIDATION / SIGN-OFF

Free course with a certificate. Press ▶ Listen to listen to the course, or read at your own pace. Tap any paragraph’s ▶ to start listening from there.

You have signed FAT reports, run capability studies and stood beside operators at start-up. You know both words. This course is about the moment they matter: when a test passes, the customer is unhappy, and someone has to decide what was really proven and who pays to fix the rest.

Register to start this free course

The course and the certificate are free. To start, create a free PMCLEAR account with your email, then enter your first name and family name exactly as they should appear on your certificate.

Two meeting questionsOne for each word. You can ask them without slides.
A requirement rewriteFive parts that make one test verify and validate.
A sign-off statementSay exactly what the evidence covers, and what it does not.
A validation trial cardGet real users in front of the design early, cheaply.

Verification

Looks back at the requirement

What did we specify, and what evidence shows we met it?

Validation

Looks forward to the person who will use it

Can the intended users get their job done with this solution under the conditions they actually face?

Unit I · Story

I. The four-minute changeover

Two technicians beside a new fixture plate on a packaging line, a shift supervisor walking up
Late afternoon on a packaging line. A new quick-change fixture plate sits on the machine bed. Two technicians stand beside a full tool cart. The shift supervisor walks up, coffee in hand.

NarratorThe fixture has been installed for a week. Today the project engineer is closing out one more requirement before the FAT report goes to the customer.

Pause

What did the four-minute test prove? What would you want to see before signing off?

The time limit was met, but only under the conditions tested. The supervisor’s question is still open, and so are two more you will see in a moment.
Good call. The stopwatch is real evidence, for those conditions. The night shift is a different question.
Too harsh. The test did prove something real. It just did not answer the supervisor’s question.
Unit II · Exercise

II. Call it: verification, validation, or both?

Many of us learned a quiet shortcut: small, early, paper checks are verification; big, late, live tests are validation. It feels right, and it is wrong often enough to cause real trouble.

The question you are answering tells you which activity you are doing. Not the size of the test, not the stage of the project, and not who holds the clipboard.

Ten situations from real projects. Make the call, then read why.

1. A designer checks the electrical drawings against the approved functional specification.

Small, early, desk work, and still verification: does this output match what we specified?

2. At FAT, the full line runs 1,000 cycles at 12 parts per minute, as the specification requires.

Big, late and live, and still verification. It checks a specified rate. Nobody’s working day was tested.

3. An operator holds a cardboard mock-up of the new control station to check reach and height.

Small, early and rough, and still validation: can this person do the job with it?

4. An electrician checks every I/O point against the I/O list during commissioning.

Every point against a specified list. Classic verification.

5. A night operator reads an alarm on the HMI and cannot tell which guard door is open.

The alarm may match the alarm list exactly. The question here is whether a real user can act on it at 2 a.m.

6. QC does a first-article inspection on the CMM against the drawing.

Measured features against specified dimensions. Verification, however thorough.

7. The specification says a maintenance technician wearing work gloves must replace a photo-eye in under ten minutes. A technician from the plant tries it.

The requirement already names the user and conditions, so one trial answers both questions.

8. A supervisor runs the new work instruction with a new hire on day one.

Can the intended user get the job done with the document? That is validation, even for paperwork.

9. The customer insists on a run-off with their real part mix, including the warped parts they actually receive, and the spec lists that mix.

Real parts, real conditions, written into the spec. Both. Without the spec line, it would be validation only, and any failure becomes a commercial discussion.

10. A safety function is tested to confirm it reaches the performance level stated in the safety requirements specification. The standard calls this “validation”.

A trap on purpose. ISO 13849-2 uses the word validation, but by our two questions this is mostly checking against a specification. Use the standard’s word in the document. Know which question you are answering.

Unit III · Story

III. The stainless-steel tray

A new stainless-steel tray on a QC bench beside its drawing, a calliper under the handle
A QC bench. A new 304 stainless tray, 600 × 400 × 80 mm, lies next to the approved drawing. A calliper rests under the bent handle. The drawing note reads: handle 110 mm long, 35 mm finger clearance, plus or minus 0.5, R5 bends, deburr all edges.

NarratorForty trays are on order. The first one has arrived from the fabricator. Priya in QC measures it before the other 39 are released.

FeatureDrawingToleranceMeasuredResult
Length × width600 × 400 mm±1.0 mm600.4 × 399.7 mmPass
Depth80 mm±1.0 mm79.6 mmPass
Handle length × clearance110 × 35 mm±0.5 mm109.6 × 34.8 mmPass
Handle bendsR5—R5 gauge fitsPass
EdgesDeburred—No burrs foundPass
Pause

Priya is asked to sign off the first article and release the other 39 trays. What should she sign today?

The readings show conformance to the drawing. They say nothing about how the tray works in an operator’s hands, and 39 more trays are about to be made.
Right. She signs exactly what the evidence supports, and uses the one tray in hand to ask the open question before the cost multiplies by 39.
Holding back her signature is not needed. Drawing conformance is real evidence. Sign it, and say what is still open.
Unit IV · Story

IV. The Excel inspection report

A supervisor reads an inspection workbook on a laptop while a lead hand waits beside tagged parts
Friday, 3:35 in the afternoon, beside the line. The workbook is open on a laptop, a lead hand waits at the bench, and tagged parts sit ready for a decision. The truck leaves at 5.

NarratorDaniel, a quality engineer, has built a workbook that flags failed bore readings. The rule is simple: diameter 12.00 millimeters, plus or minus 0.05. Before releasing it, he tests it with values he already knows the answer to.

Test value (mm)Why this valueExpectedWorkbook
12.000NominalPassPass
12.050Upper limit, exactlyPassPass
12.051Just above upper limitFailFail
11.950Lower limit, exactlyPassPass
11.949Just below lower limitFailFail
BlankMissing readingMissingMissing
“12,02”Comma decimal from an exported fileErrorError

Keep this set. Nominal, each limit, just outside each limit, a blank and a wrong format: these seven values verify almost any pass/fail rule, in a spreadsheet, a PLC or a vision system.

Pause

Daniel says the workbook is ready. What has he shown?

His tests show the flags are right. They do not show that the report leads someone to the right decision.
Yes. Good verification work, and an open validation question.
Known test values are exactly how you verify rules. They prove something real, even without production data.
Unit V · Story

V. When the gap shows up at SAT

A customer plant manager and an integrator project manager at the machine during site acceptance
Three months later, at the customer’s plant. The changeover fixture is installed. The customer’s plant manager has the FAT report in his hand.
Pause

Is this a defect to fix under warranty, or a change?

Maybe, but not automatically. If the spec never mentioned one operator, the requirement was incomplete, and that is a different conversation.
Yes. And notice how much depends on paperwork written months earlier.
Technically defensible, commercially dangerous. You still need SAT signed, and you still want the next order.
Unit VI · Part 1 · For your next meeting

VI-1. A line you can use tomorrow

Each role gets one sentence to say out loud in the next meeting. It works because it makes the room answer one of the two questions.

Phrases that should make you pause

You will hear these in design reviews, FAT meetings and Friday afternoons. Each one hides a mix-up between the two questions.

You hearWhat is mixed upWhat you can say
“It passed FAT, so it works.”Verification taken as validation“It met the spec under FAT conditions. Who has tried it the way the plant will run it?”
“The customer will validate at SAT.”Validation pushed to the most expensive moment“What can we let an operator try before it ships?”
“We validated the drawing.”A drawing check is verification“Against which requirement? And has a user seen a mock-up?”
“Operators will get used to it.”An open validation gap with no owner“Let’s watch one try it and decide if that is acceptable.”
“It’s within tolerance.”True, and maybe not enough“Agreed. Is it the right tolerance for the job?”
Unit VI · Part 2 · Closing

VI-2. Back to the night shift

The same packaging line at night, one operator at the machine
The same packaging line, now at night. Lower lighting, one operator at the machine, the tool cart gone.

NarratorWe started here. Let’s finish here.

Pause

The two technicians finished in four minutes. What can you sign off today, and what would you test next?

The requirement as written may be met, but you now know three things the four minutes did not cover.
That is the course in one answer.
The day-shift result is real evidence. Sign what it supports, then test what is still open.
Unit VII · Practice

VII. Practice checks

Five quick checks. Pick an answer to see the explanation. You can change your answer at any time; practice does not count toward the certificate.

1. Running the full production line for eight hours at FAT is always validation.

If the run checks a specified rate, uptime or reject limit, it is verification. The question decides, not the size of the test.

2. If a requirement does not say where the clock starts and stops, a timed test gives weak verification evidence.

Without an agreed pass definition, two honest people can time the same changeover and get four minutes and seven.

3. A tray made exactly to drawing has been validated.

Made to drawing is verification. Whether an operator can use it with gloves is a separate question.

4. Inviting a customer operator to FAT can give early validation evidence.

A real user trying the real task in your shop finds the gap before SAT, when it is still cheap to fix.

5. A good sign-off says what the evidence does not cover.

Stating what is still open protects the signer, the project and the customer. A bare “Pass” reads like a promise.

Unit VIII · Final assessment

VIII. The label printer at the cold dock

One scenario, seven decisions. You will see the explanations after you submit. Six correct out of seven passes. If you do not pass, you can review the explanations and try again.

A print-and-apply label unit on a conveyor in a cold dock, with an overhead scanner and a trailer at the door
The print-and-apply unit at the customer’s cold dock.

The requirement

“The print-and-apply unit shall print and apply a GS1-128 shipping label to each case within 6.0 seconds. Labels shall be scannable.”

The FAT record

200 cases run at a 6.0 s cycle. Every label printed and applied. Labels scanned at the bench with a handheld scanner: 200 of 200 read. Room temperature 21 °C. Cardboard cases supplied by the integrator. Label data checked against the customer’s GS1 label specification, Rev C, on 10 sampled labels: all correct.

What you learn at the pre-shipment meeting

At the customer’s dock, cases come straight from a −20 °C freezer into a 2 °C dock and carry condensation. Labels are read by a fixed overhead scanner about 2 m above the conveyor, at belt speed. The customer uses their own case stock.

Part 1 and 2. For each statement, decide: can you sign it off today from the FAT evidence, or is it still open?

1. The print-and-apply cycle meets 6.0 seconds under FAT conditions.

2. Label data matches GS1 specification Rev C, for the 10 labels sampled.

3. Every one of the 200 labels carried correct data.

4. Labels read with a handheld scanner at the bench, 200 of 200, at 21 °C.

5. Labels stay on cold, wet cases from the freezer.

6. The dock’s overhead scanner reads the labels at belt speed.

Part 3. What evidence do you need next?

7. Choose the best next step before shipment.

Rate this course

Pass the final assessment to rate the course (optional).

Your certificate

Your free certificate is issued after you complete every unit and pass the final assessment.
    Take it to work

    Your worksheet

    Pick one requirement from your current project. Fill in both sides, then save it as a PDF or print it for your next design review or FAT meeting.

    Which one are we doing right now?

    PMCLEAR CPD / PDH worksheet

    Verification: What did we specify, and what evidence shows we met it?

    Validation: Can the intended users get their job done with this solution under the conditions they actually face?

    Verification

    Validation

    Sign-off

    Next action

    About this training

    Verification & Validation — 2-Hour CPD / PDH Course is a self-paced online professional development course by PMCLEAR for engineers, project managers and quality control professionals in Canada, the United States and internationally. It teaches how to tell, in a live meeting, whether a test or check is verification (did we meet what we specified?) or validation (can the intended users do their job under real conditions?), and how to sign off only what the evidence shows.

    Learning outcomes

    Course content (8 units)

    1. The four-minute changeover
      Timed changeover evidence, missing pass definitions, single trials, requirement rewrite
    2. Call it: verification, validation, or both?
      Ten classification exercises from design review, FAT, commissioning and quality
    3. The stainless-steel tray
      First-article inspection, glove trial, cost of late discovery, validation trial card, sign-off statement
    4. The Excel inspection report
      Test-value design for pass/fail rules, decision-centered validation of reports
    5. When the gap shows up at SAT
      Specification, FAT records, change versus warranty, protecting acceptance
    6. A line you can use tomorrow; back to the night shift
      Meeting language for engineers, project managers and QC; closing decision
    7. Practice checks
      Five Yes / No practice checks with explanations
    8. Final assessment
      A seven-decision scenario: what can be signed off, what is open, what evidence is needed next

    Format and completion requirements

    Hours, subject type and where it counts

    Course duration: 2 hours. Delivery: self-paced online. Provider: PMCLEAR. Acceptance of CPD / PDH hours is decided by the learner's professional regulator or licensing board; this course is not accredited or pre-approved by an engineering regulator.

    Go to the course

    Read or listen
    Recorded 0 min 0 s · minimum 72 min Sections 0/0 Check 0/20 Assessment —