Sprint planning: goal, capacity and commitment

Agile and hybridFree preview
Goal: After this lesson you can run Sprint Planning around its three topics (why, what and how), write a useful Sprint Goal, size the sprint using velocity and capacity, explain what the team commits to, and handle changes and surprises during the sprint.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“Just take the top ten items”

At the transit agency's third Sprint Planning, the Product Owner arrives with a list: “These are the top ten items. Please take all of them.” The Developers look at the list: ten unrelated items, from a new map style to a bug in the fare calculator, adding up to about 45 points. Their velocity is about 28, and two people have training days this sprint.

Previous sprints followed the same pattern. The team accepted everything, worked long days, finished six or seven items, and ended each sprint with a sense of failure. Stakeholders saw a mix of small changes but nothing that felt like progress.

Sprint Planning in Scrum is designed to avoid exactly this. It starts not with a list, but with a question: why is this sprint valuable? It lets the people doing the work decide how much fits. And it ends with a plan the team believes in.

This lesson walks through Sprint Planning step by step, using the transit team as an example: the three topics, the Sprint Goal, capacity, what “commitment” really means, and what to do when reality changes mid-sprint.

2The purpose of Sprint Planning

Sprint Planning starts the sprint by laying out the work to be performed. The entire Scrum Team collaborates on the plan, and other people (for example, an expert) can be invited to provide advice.

It is timeboxed to a maximum of eight hours for a one-month sprint; shorter sprints usually need less (about two to four hours for a two-week sprint). The Product Owner makes sure participants are prepared to discuss the most important Product Backlog items and how they map to the Product Goal.

The result is the Sprint Backlog: the Sprint Goal, the Product Backlog items selected for the sprint, and an actionable plan for delivering the increment.

3See it in one picture: why, what and how

The three topics of Sprint PlanningWHYSprint Goalwhole Scrum TeamWHATSelected itemsDevelopers selectHOWThe planDevelopers createSprint BacklogTimebox: at most 8 hours for a one-month sprint.
Sprint Planning answers three questions. The whole Scrum Team crafts the goal (why); the Developers select the items (what) and create the plan (how). Together they form the Sprint Backlog.

4How it looks on the exam

Exam-style question 1. During Sprint Planning, the Product Owner insists that the team take 40 points of work. The Developers' recent velocity is 30 points, and one developer will be on vacation. What should happen?
A. The Developers accept 40 points to meet the Product Owner's needs
B. The Scrum Master decides on a compromise of 35 points
C. The Developers select the amount they forecast they can complete
D. The team accepts 40 points and plans overtime for the gap
Show the answer and the decode
Answer: C.
What it means
Pressure to overcommit, reduced capacity.
What is the question really asking?
Who decides the amount of work.
Key words / trigger
“insists that the team take 40 points”
PMP logic
The Developers select how much they can complete, using past performance and capacity: probably fewer than 30 points this sprint. The PO decides the order of the backlog. The Scrum Master can coach the PO on this rule.
Why the wrong answer looks attractive
A: overcommitment leads to undone work or quality cuts. B: the Scrum Master does not decide the amount. D: planned overtime is not sustainable and hides real capacity.

5Remember this

Your memory card

  • Sprint Planning creates the Sprint Backlog: Sprint Goal + selected items + plan
  • Why: the whole Scrum Team crafts a Sprint Goal (one outcome)
  • What: the Developers select items, using velocity, capacity and the DoD
  • How: the Developers plan the work, often in tasks of one day or less
  • Commitment = Sprint Goal; selected items are a forecast
  • Timebox: up to 8 hours for a one-month sprint
  • During the sprint: scope renegotiated with the PO, goal and quality protected; urgent requests go to the PO
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (Topic one: why is this sprint valuable?, Topic two: what can be Done this sprint?, Sizing the sprint: velocity and capacity, Topic three: how will the work get done?, What the team commits to, Before Sprint Planning: refinement, During the sprint: when reality changes, Facilitating Sprint Planning well, Sprint Planning in hybrid projects, Common mistakes, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
Open the full lesson → Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.