“Just take the top ten items”
At the transit agency's third Sprint Planning, the Product Owner arrives with a list: “These are the top ten items. Please take all of them.” The Developers look at the list: ten unrelated items, from a new map style to a bug in the fare calculator, adding up to about 45 points. Their velocity is about 28, and two people have training days this sprint.
Previous sprints followed the same pattern. The team accepted everything, worked long days, finished six or seven items, and ended each sprint with a sense of failure. Stakeholders saw a mix of small changes but nothing that felt like progress.
Sprint Planning in Scrum is designed to avoid exactly this. It starts not with a list, but with a question: why is this sprint valuable? It lets the people doing the work decide how much fits. And it ends with a plan the team believes in.
This lesson walks through Sprint Planning step by step, using the transit team as an example: the three topics, the Sprint Goal, capacity, what “commitment” really means, and what to do when reality changes mid-sprint.