PMP lesson · Closing & Integration · Closing the project · lesson 1 of 4 · about 7 minutes
Closing a project or phase (including early termination)
All approaches (agile closes releases and products similarly)Free preview
Goal: After this lesson you can list the closing activities in the right order and close properly, even when a project is terminated early.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
1The situation
Everyone wants to leave
The robot cell has been accepted. The functional managers want their engineers back immediately. The subcontractor still has an open claim for waiting time, two punch-list items remain, and nobody has scheduled the lessons-learned session.
Across the plant, a different project was just cancelled by the steering committee. Its team is being approached by other managers, and the vendor asks: “Should we keep working?”
Both projects need the same thing: a proper close.
2What closing includes
Closing a project (or a phase) finishes all activities in an orderly way:
Accept
Deliverables
Formal acceptance against criteria.
Settle
Contracts
Claims resolved, procurements closed.
Learn & release
People and knowledge
Lessons learned, archive, release resources.
Close formally, in order: accept → close contracts → transfer → lessons → report → archive → release → sign-off. Keep key people until lessons and records are done.
3The closing activities
1 · Confirm acceptance
All deliverables formally accepted against criteria.
Exam-style question 1. After a portfolio review, the steering committee terminates a partially completed project. Team members are being approached by other managers, and the vendor asks whether to continue. What should the project manager do NEXT?
A. Perform the closing activities: document status and reasons, settle procurements, capture lessons learned and release resources formally
B. Release the team and stop the vendor; documentation is unnecessary
C. Continue to a natural stopping point
D. Appeal the decision
Show the answer and the decode
Answer: A.
What it means
Legitimate early termination.
What is the question really asking?
The next step.
Key words / trigger
“terminates a partially completed project”
PMP logic
Terminated projects are closed formally.
Why the wrong answer looks attractive
Stopping everything at once seems efficient, but leaves contracts and knowledge unresolved.
5Remember this
Your memory card
Close in order: accept → contracts → transfer → lessons → report → archive → release → sign-off