Goal: After this lesson you can close a contract correctly: acceptance, punch list, claims, payments, warranty, records and formal notice.

1The situation

Almost closed

All conveyor deliverables were installed and accepted. The project manager wants to close the subcontract and release the team. But the subcontractor has an open claim for site waiting time, two punch-list items remain, and the final invoice is waiting.

Closing now would leave money, liability and a dispute hanging, possibly for years.

2Close only when everything is settled

A contract is closed when all obligations on both sides are met:

Accepted
Deliverables
Formally accepted; punch list done or agreed.
Settled
Claims
Disputes resolved, negotiation first.
Paid & recorded
Finance and files
Final payment, warranty start, complete records, written closure.
Open claim or unfinished items → resolve first, then close formally. Don't use payment as leverage to force a claim's withdrawal.

3Contract closure checklist

Before closing a contractCheck
All deliverables acceptedFormal acceptance against criteria
Punch-list itemsClosed or formally agreed (e.g. retention until done)
Claims and disputesSettled (negotiation first)
PaymentsFinal invoice approved; retention released per contract
WarrantyStart date and terms documented
RecordsContract file complete; procurement audit / lessons
Formal noticeWritten confirmation that the contract is closed
Every line done before the formal closure notice.

4How it looks on the exam

Exam-style question 1. All deliverables under a subcontract are installed and accepted, and the project manager wants to close it. The subcontractor has an open claim for additional site waiting time, and two minor punch-list items remain. What should the project manager do?
A. Close the contract immediately
B. Close and handle the claim informally afterwards
C. Resolve the claim and the punch-list items, confirm all obligations are met, then formally close the contract
D. Withhold final payment until the claim is withdrawn
Show the answer and the decode
Answer: C.
In simple English
Open claim and open items at closure.
What is the question really asking?
The right sequence.
Key words / trigger
“open claim … punch-list items remain”
PMP logic
Close only after claims are settled and obligations met.
Why the wrong answer looks attractive
Closing quickly to free the team leaves the dispute open.

5Remember this

Your memory card

  • Close when all obligations are met: acceptance, punch list, claims, payment
  • Settle claims first (negotiation); never use payment as leverage
  • Document warranty, complete records, issue written closure
  • Procurement audit → lessons for future procurements
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (After closure)
  • a worked example
  • the common traps (wrong vs right)
  • 2 exam-style questions with the decode
  • a 3-question quick check
Open the full lesson → Create a free account