PMP lesson · Delivery Approach · Choosing how to deliver · lesson 2 of 4 · about 6 minutes
The predictive life cycle: phases and gates
Predictive · hardware parts of hybrid projectsFree preview
Goal: After this lesson you can describe predictive phases and gates, explain when predictive fits, and reduce its typical risks.
1The situation
Why plan the steel first?
You cannot “iterate” a 4-tonne robot base. Once the steel is cut and welded, changing it costs days and thousands of dollars. That is why the robot cell's mechanical work is designed, reviewed and approved before fabrication starts.
The predictive life cycle is not old-fashioned. It is the right tool when the work is clear and changes are expensive.
2Phases and gates
A predictive project moves through phases (for example concept, design, build, install, close). At the end of each phase, a phase gate reviews the results against exit criteria and decides: go, no-go or go with conditions.
Plan
Up front
Scope, schedule and cost baselines before execution.