“So what will it cost in the end?”
A city utility is replacing 1,000 old water meters at a budgeted $100 each: BAC = $100,000. By the status date, 500 meters should have been installed (PV = $50,000). Only 400 are done (EV = $40,000), and the work has cost $60,000 (AC).
The utility director asks the obvious question: “So what will the whole job cost?” You already know the CPI (0.67) and SPI (0.80) from the previous lesson. But they describe the past. The director needs the future.
The answer depends on why the project is over budget. If a crew damaged a delivery once, the rest may go to plan. If each meter simply takes longer than estimated, the overrun will continue. If old pipes need new fittings that nobody budgeted for, the original estimate is no longer valid.
This lesson shows how to turn earned value data into a forecast, how to choose the right formula for the right cause, and how to present the result honestly.