The daily stand-up

Agile and hybridFree preview
Goal: After this lesson you can describe the purpose of the daily stand-up and fix its most common problems.

1The situation

The 45-minute stand-up

The MES team's “15-minute” daily meeting now takes 45 minutes. Developers discuss technical problems in depth while others wait. Several people have started skipping it.

A stand-up that wastes everyone's time is worse than no stand-up. Fortunately, the fix is simple.

2Purpose

The daily stand-up (daily scrum) is a short event for the team to coordinate toward the sprint goal and surface impediments. It is timeboxed to 15 minutes.

For the team
Coordination
Members talk to each other, not to a manager.
15 minutes
Timeboxed
Same time, same place; short.
Parking lot
Details after
Problems are solved afterwards with only the people involved.
Long discussion in the stand-up → keep the timebox and move it to the parking lot. Impediments → the servant leader helps remove them.

3What the stand-up is and isn't

Purpose

The team coordinates toward the sprint goal and spots impediments. 15 minutes, same time and place.

Typical focus

What moved us toward the goal? What's next? What's blocking us? (or walk the board right to left)

Not for

Status reports to a manager · long technical discussions · problem-solving with the whole team waiting
Short, focused, owned by the team.

4How it looks on the exam

Exam-style question 1. The daily stand-up has grown to 45 minutes because members discuss technical problems in depth while others wait. Some members now skip it. What should the project manager suggest?
A. Replace it with a weekly meeting
B. Keep it to 15 minutes focused on the sprint goal and impediments, and move detailed problem-solving to follow-up discussions with only the people involved
C. Allow it to continue
D. Let the PM run it and decide who speaks
Show the answer and the decode
Answer: B.
In simple English
The stand-up lost its purpose.
What is the question really asking?
The fix.
Key words / trigger
“grown to 45 minutes”
PMP logic
Timebox it and use a parking lot for details.
Why the wrong answer looks attractive
Technical discussion is valuable, but not with everyone waiting.

5Remember this

Your memory card

  • Stand-up = team coordination toward the sprint goal, 15 minutes
  • Not a status report; not a problem-solving session
  • Parking lot for details, with only the people involved
  • Repeated blockers → the servant leader removes them
The full lesson in the PMCLEAR app also has:
  • a worked example
  • the common traps (wrong vs right)
  • 2 exam-style questions with the decode
  • a 3-question quick check
Open the full lesson → Create a free account