Home › PMP lessons › Agile Metrics & Events

PMP lesson · Agile Metrics & Events · Agile events · lesson 1 of 3 · about 25 minutes

The Daily Scrum (daily stand-up)

Agile and hybridFree preview
Goal: After this lesson you can explain the purpose and rules of the Daily Scrum as defined in the 2020 Scrum Guide, choose a format that focuses on the Sprint Goal, handle impediments and side discussions correctly, and recognize when a stand-up has turned into a status meeting.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“Every morning we report to the manager”

At a hospital's IT department, the team building a new patient-portal feature holds a stand-up every morning. It takes 35 minutes. Each person turns to the department manager and lists what they did yesterday. The manager asks questions, gives instructions, and sometimes starts a technical debate that the rest of the team quietly waits through.

Developers say, privately, that the meeting is the least useful part of their whole day. Problems are mentioned (“still waiting for the test database”) but nobody does anything about them. The Sprint Goal is never mentioned at all, not even once a week.

In Scrum, this event is called the Daily Scrum. It has a clear purpose, a 15-minute timebox and a specific audience: the Developers. It is not a report to a manager; it is the team's daily planning meeting.

This lesson explains, step by step, what the Daily Scrum is for, how to run it well in practice, what to do with problems and long discussions, and how to recognize and fix the common anti-patterns.

2Purpose of the Daily Scrum

According to the 2020 Scrum Guide, the purpose of the Daily Scrum is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary, adjusting the upcoming planned work. It is a short daily inspect-and-adapt loop inside the sprint.

The Guide also lists its benefits: it improves communication, identifies impediments, promotes quick decision-making and, as a result, eliminates the need for other meetings. A good Daily Scrum replaces many small coordination emails and conversations.

Daily Scrum = inspect progress toward the Sprint Goal + adapt the plan for the next day.

3See it in one picture: walk the board

Walk the board from right to leftTo doIn progressReviewDoneblocked 3 daysStart at Done, move left: what can we finish today?15 minutes · same time and place · for the Developers
Start with the work closest to Done and move left. The highlighted item has been blocked for three days: it becomes the first topic, and someone owns its removal right after the meeting.

4How it looks on the exam

Exam-style question 1. A functional manager attends the Daily Scrum every morning and asks each developer for a status update, which often makes the meeting run 30 minutes. What should the Scrum Master do?
A. Let the manager continue, since status is useful
B. Coach the manager: the event is for the Developers
C. Cancel the Daily Scrum and email status instead
D. Ask the Product Owner to run the meeting
Show the answer and the decode
Answer: B.
What it means
A manager turns the Daily Scrum into a status meeting.
What is the question really asking?
The Scrum Master's response.
Key words / trigger
“asks each developer for a status update”
PMP logic
The Daily Scrum is the Developers' event for inspecting progress and adapting the plan. The Scrum Master coaches the manager and offers other sources of status, such as radiators. The manager may observe quietly if the team agrees.
Why the wrong answer looks attractive
A: allows the event to lose its purpose and timebox. C: removes the team's daily inspection. D: the PO does not run the Daily Scrum.

5Remember this

Your memory card

  • Purpose: inspect progress toward the Sprint Goal and adapt the Sprint Backlog
  • For the Developers; PO and SM join as Developers only if working on sprint items
  • 15 minutes, same time and place, every working day
  • 2020 Scrum Guide: no mandatory questions; walking the board keeps the focus on finishing
  • Impediments are raised in the meeting and removed afterward; the Scrum Master causes their removal
  • Side discussions go to a parking lot, right after the meeting
  • Not a status meeting; give stakeholders status through radiators
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (Who it is for, Timebox, time and place, Structure: the Developers choose, Walking the board, What a good Daily Scrum sounds like, The Scrum Master's role, Impediments, Side discussions: the “parking lot”, Anti-pattern: the status meeting, Other anti-patterns, Remote and hybrid teams, Daily coordination in predictive projects, How PMI tests the Daily Scrum, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check