“Twenty slides and no questions”
At the end of each sprint, the city's permit-application team presents its work to the building services department. The Scrum Master prepares twenty slides with screenshots, a list of completed stories and the velocity chart. Stakeholders listen politely, ask few questions and leave after forty minutes.
Two sprints later, the permit inspectors finally try the new online scheduling feature in real life and discover it does not match how inspections are actually booked. Weeks of work need to change. Nobody had raised the problem in the reviews, because nobody had actually used the software there.
The Sprint Review is meant to prevent exactly this. It is not a presentation for approval; it is a working session where stakeholders see and use the real increment, discuss what has changed in their world, and help decide what to do next.
This lesson explains the purpose of the Sprint Review, how to prepare and run it, what happens to unfinished work and feedback, and how it differs from the retrospective and from formal acceptance.