The Sprint Review: inspecting the product with stakeholders

Agile and hybridFree preview
Goal: After this lesson you can explain the purpose and rules of the Sprint Review as defined in the 2020 Scrum Guide, run it as a working session rather than a demonstration, handle unfinished work and stakeholder feedback correctly, and distinguish it from the Sprint Retrospective and from formal acceptance.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“Twenty slides and no questions”

At the end of each sprint, the city's permit-application team presents its work to the building services department. The Scrum Master prepares twenty slides with screenshots, a list of completed stories and the velocity chart. Stakeholders listen politely, ask few questions and leave after forty minutes.

Two sprints later, the permit inspectors finally try the new online scheduling feature in real life and discover it does not match how inspections are actually booked. Weeks of work need to change. Nobody had raised the problem in the reviews, because nobody had actually used the software there.

The Sprint Review is meant to prevent exactly this. It is not a presentation for approval; it is a working session where stakeholders see and use the real increment, discuss what has changed in their world, and help decide what to do next.

This lesson explains the purpose of the Sprint Review, how to prepare and run it, what happens to unfinished work and feedback, and how it differs from the retrospective and from formal acceptance.

2Purpose of the Sprint Review

The 2020 Scrum Guide defines the purpose of the Sprint Review as to inspect the outcome of the sprint and determine future adaptations. The Scrum Team presents the results of its work to key stakeholders, and progress toward the Product Goal is discussed.

It is the main moment where the people who build the product and the people who use or fund it look at the real result together. Its value comes from the conversation: feedback, new information and decisions about what comes next.

Sprint Review = inspect the increment with stakeholders + adapt the Product Backlog.

3See it in one picture: a working session

A Sprint Review as a working session1. ContextPO: goal, what is Done, what is not2. DemonstrateWorking increment, used for real3. FeedbackStakeholders try it and react4. Market & changesWhat has changed outside?5. Adapt the backlogReorder, add, remove items6. Look aheadRelease forecast, next stepsA conversation about the product, not a slide show
A good Sprint Review moves from context, to the real increment in stakeholders' hands, to feedback, to decisions about the Product Backlog and the forecast.

4How it looks on the exam

Exam-style question 1. During a Sprint Review, a key stakeholder asks for a new feature that was not planned. What should happen?
A. The Developers add it to the current sprint immediately
B. The Scrum Master decides whether it is important enough
C. The Product Owner captures it in the Product Backlog
D. The team rejects it, since the sprint scope is fixed
Show the answer and the decode
Answer: C.
What it means
New stakeholder request during the review.
What is the question really asking?
How to handle it.
Key words / trigger
“asks for a new feature”
PMP logic
Feedback and requests go to the Product Owner, who adds them to the Product Backlog and orders them against other work. If it were critical, the PO might place it at the top for the next sprint.
Why the wrong answer looks attractive
A: bypasses the PO and disrupts planning. B: the Scrum Master does not decide priorities. D: rejecting feedback misses the purpose of the review.

5Remember this

Your memory card

  • Purpose: inspect the sprint's outcome and determine future adaptations; discuss progress toward the Product Goal
  • A working session, not a presentation: stakeholders use the real increment
  • Scrum Team + key stakeholders invited by the PO; up to 4 hours for a one-month sprint
  • Only Done work is shown as complete; undone items return to the backlog
  • Feedback goes to the Product Backlog via the PO; the output is a revised backlog
  • Not a release gate or contractual acceptance
  • Review = product with stakeholders; retrospective = process within the team
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (A working session, not a presentation, Who attends, Timebox and timing, Typical flow, Discussing the market and the Product Goal, Facilitating good feedback, Is the review adding value?, Only Done work is shown as complete, Feedback goes to the Product Backlog, The Sprint Review is not a release gate or acceptance meeting, Preparing a good review, Sprint Review versus Sprint Retrospective, Reviews in predictive and hybrid projects, Common mistakes, How PMI tests the Sprint Review, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check