Business case and project selection: NPV, IRR, payback and benefit-cost ratio

All approachesFree preview
Goal: After this lesson you can explain what a business case contains, calculate present value and NPV by discounting cash flows, interpret IRR, payback, benefit-cost ratio and ROI, and choose between projects using both financial and strategic criteria.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
▶ Watch this lesson (video)
Open on YouTube ↗

1The situation

Two good ideas, one budget

You work in the project management office of a regional grocery chain. The executive team has $500,000 for improvement projects this year and two proposals on the table.

Project A, self-checkout lanes, costs $500,000 and should save about $150,000 in labor every year for five years. Project B, new warehouse software, also costs $500,000. Its savings start slowly while staff learn the system ($50,000 in year 1), then grow to $250,000 a year by year 4.

Over five years, Project A saves $750,000 and Project B saves $850,000. Project A pays back its cost sooner. The chief financial officer says, “Payback is not enough. Show me the NPV at our 8% discount rate.”

This lesson explains why money received later is worth less today, how to calculate net present value (NPV) step by step, what IRR, payback, benefit-cost ratio and ROI each tell you, and why the numbers are only part of the decision.

2Where the business case fits

Organizations have more good ideas than money and people. Portfolio management decides which projects to fund, based on strategy. The document that argues for one project is the business case.

The business case comes before the project charter. It answers: why should we do this, what will it cost, what value will it bring, what are the options (including doing nothing), and what are the risks? It is usually owned by the sponsor, often with help from the project manager or a business analyst.

If the business case is approved, the project charter formally authorizes the project and the project manager. A benefits management plan then describes how and when the promised benefits will be measured. The business case is not a one-time document: it is checked at stage gates and whenever major changes happen, to confirm the project is still worth doing.

Order: strategy → business case (why and is it worth it?) → charter (authorization) → plan (how). On the exam, the business case is the document that justifies the project.

3See it in one picture: money later is worth less

Present value of $150,000 by year received, at 8%150kNow139kYr 1129kYr 2119kYr 3110kYr 4102kYr 5What $150k is worth today (8% discount rate)
Each bar is $150,000 received in a different year, discounted at 8%. The further away the money, the less it is worth today. This is why NPV, not the simple total, is used to compare projects.

4How it looks on the exam

Exam-style question 1. A sponsor must choose one of two projects. Project 1 has an NPV of $260,000 and lasts four years. Project 2 has an NPV of $210,000 and lasts two years. Both fit the strategy equally well. Which project should be selected?
A. Project 2, because it delivers its benefits two years sooner
B. Project 1, because its net present value is higher
C. Project 2, because its value per year of duration is higher
D. Either project, because both have a positive NPV
Show the answer and the decode
Answer: B.
What it means
Two projects, two NPVs, different durations.
What is the question really asking?
The selection based on financial value.
Key words / trigger
“NPV … lasts four years”
PMP logic
NPV already accounts for when the money arrives, so the duration is already in the number. Choose the highest NPV: Project 1. If the projects were not mutually exclusive and money allowed, both could be funded because both are positive.
Why the wrong answer looks attractive
A: counts time twice; NPV already discounts later benefits. C: dividing NPV by duration is not a valid selection method. D: both are acceptable, but the question asks which one to select when only one can be chosen.

5Remember this

Your memory card

  • Business case = why the project is worth doing; it comes before the charter and is reviewed at gates
  • Money later is worth less: PV = FV ÷ (1 + r)t; the discount rate is set by finance
  • NPV = sum of discounted cash flows. Above 0 adds value; choose the highest NPV; never count time twice
  • IRR = rate where NPV = 0; accept if above the hurdle rate; NPV wins if they conflict
  • Payback: shortest is best, but it ignores time value and everything after payback
  • BCR above 1.0 is good; ROI may ignore timing
  • Sunk costs are ignored; opportunity cost = value of the best option not chosen
  • Mandatory (legal, safety) projects can proceed with negative NPV
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (What a business case contains, Outputs, outcomes and benefits, The time value of money, The discount rate: who chooses it?, Net present value (NPV), step by step, Internal rate of return (IRR), Payback period, Benefit-cost ratio and ROI, Costs that matter, and costs that do not, Beyond the numbers: strategic and non-financial criteria, Business cases in agile and hybrid work, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
  • an interactive calculator
Open the full lesson → Create a free account