Motivation: what really drives people
All approachesFree preview
Goal: After this lesson you can explain the main motivation theories and choose a response that addresses the real cause of low motivation.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
1The situation
“Any trainee could do this”
Your most experienced commissioning technician has been verifying I/O lists for three months. His pay is good, his supervisor is fair, the working conditions are fine. But he has become quiet and slow, and he told a colleague: “Any trainee could do this job.”
The sponsor suggests a bonus. Would that help?
Motivation theories explain why money alone often doesn't fix this, and what does.
2Herzberg: two kinds of factors
Herzberg's two-factor theory is the most tested on the PMP:
Exam-style question 1. An engineer recently received a raise, has good working conditions and a fair supervisor, but says she feels 'stuck' because her work never changes and her ideas are never recognised. According to Herzberg, what is missing?
A. Hygiene factors such as pay
B. Motivators such as recognition, responsibility and growth
C. Basic safety needs
D. Better working conditions
Show the answer and the decode
Answer: B.
What it means
Pay and conditions are good, but she is unmotivated.
What is the question really asking?
What Herzberg says is missing.
Key words / trigger
“raise … good working conditions … never recognised”
PMP logic
Hygiene factors are satisfied; motivators are missing.
Why the wrong answer looks attractive
More money is the obvious idea, but pay is a hygiene factor and is already fine.