Burndown and burn-up charts

Agile and hybridFree preview
Goal: After this lesson you can build and read sprint and release burndown charts and burn-up charts, recognize the common patterns and what they mean, explain why burn-up charts show scope change better, and use these charts for forecasting without turning them into tools of micromanagement.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“The chart says we're behind. Are we?”

Exactly halfway through a two-week sprint, the transit app's Scrum Master shares the sprint burndown chart at the Daily Scrum. The ideal line runs neatly from 40 points down to zero. The team's actual line has hardly moved: after five days, 35 points remain.

A Developer protests: “We're working on everything! Most stories are 80% done.” Another says: “That's the problem. Nothing is finished.” The department manager, looking at the same chart, asks whether the team should work the weekend.

Burn charts are simple pictures, but reading them well takes some practice and context. A flat line can mean blocked work, too many items in progress, or stories that are too large. A rising line can mean new work. And the same chart can help a team improve, or be misused to pressure it.

This lesson explains, step by step, sprint and release burndowns, burn-up charts, how to read their patterns, and how to use them for honest forecasting.

2What burn charts show

Burn charts show progress over time in a single picture. A burndown chart shows the work remaining: it starts high and should fall to zero. A burn-up chart shows the work completed, rising toward a line that represents the total scope.

They are among the most common information radiators in agile teams: large, visible displays that make progress transparent to everyone without meetings or reports. Their power is simplicity: anyone can understand a line that should reach zero by a date.

The 2020 Scrum Guide does not require burn charts; it says various practices exist to forecast progress, like burn-downs, burn-ups or cumulative flows. Teams choose the tools that help them.

3See it in one picture: a sprint burndown

Sprint burndown: ideal vs actual0102030400246810idealactual: flat startends with 4 points not Done →Sprint dayPoints remaining
The grey dashed line is the ideal pace. The team's red line stays flat while many stories are in progress, then falls steeply at the end. Four points are not Done and return to the Product Backlog.

4How it looks on the exam

Exam-style question 1. A sprint burndown chart has been flat for the first five days of a ten-day sprint, although the Developers report that they are busy. What is the most likely explanation?
A. The Developers are not working on sprint items
B. The ideal line was drawn incorrectly at planning
C. Many items are in progress, but few or none are Done
D. The Product Owner has removed items from the sprint
Show the answer and the decode
Answer: C.
What it means
Busy team, flat burndown.
What is the question really asking?
The likely cause.
Key words / trigger
“flat … although the Developers report that they are busy”
PMP logic
A flat line with a busy team usually means too much work in progress and nothing finishing, or blockers. The response is to limit WIP and swarm. If the team were idle, a flat line would mean something else, but that is not indicated.
Why the wrong answer looks attractive
A: contradicts the report that they are busy. B: the ideal line does not change actual progress. D: removing items would make the line drop, not stay flat.

5Remember this

Your memory card

  • Burndown: work remaining over time; burn-up: work completed plus a separate scope line
  • Sprint burndown is the Developers' tool; release charts serve the PO and stakeholders
  • Flat = nothing finishing · steep end = items too large · rising = scope added · above zero at end = not Done
  • Only Done work burns down; no partial credit
  • Burn-ups separate pace from scope change; better for stakeholder conversations
  • Forecast with ranges by extending trends; update every sprint
  • Not in the Scrum Guide as a requirement; never use charts to judge individuals
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (The sprint burndown, Points or tasks?, Building a burn chart step by step, Reading sprint burndown patterns, Release burndown, Burn-up charts, Forecasting with burn charts, Who the charts are for, Using burn charts well, Burn charts in Kanban and continuous flow, Burn charts and earned value, Common mistakes, How PMI tests burn charts, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
Open the full lesson → Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.