PMP lesson · Procurement · Procurement · lesson 1 of 2 · about 30 minutes

Contract types and who carries the risk

Predictive · agile contracts (fixed budget, variable scope) in hybridFree preview
Goal: After this lesson you can explain the main contract families and who carries cost risk in each, choose a suitable type for a given level of scope certainty, calculate fees and prices for incentive contracts including the point of total assumption, and describe contract approaches used in agile work.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“Just make them give us a fixed price”

A provincial transit authority needs three things from outside suppliers this year: 40 identical bus shelters, a new passenger-information display system that has never been built before, and on-call engineering support for unpredictable repairs.

The finance director wants the same answer for all three: “Fixed price. That way the supplier carries the risk, not us.” The engineering manager disagrees: “No serious company will quote a fixed price for a system nobody has designed yet. Or if they do, the price will be enormous.”

Both have a point. The contract type decides who pays when costs turn out higher than expected, and how hard the seller works to control costs. The right choice depends on how well the scope can be defined.

This lesson explains the three contract families, the variations inside each, how incentive fees and the point of total assumption are calculated, and how agile projects adapt contracts to changing scope.

2Why the contract type matters

A contract is a legally binding agreement: the seller provides specified products or services, and the buyer pays. Every contract also allocates risk: if the work costs more than expected, someone pays for it. The contract type decides who.

Sellers are not charities. If they carry more risk, they include a risk premium in their price. So pushing all risk to the seller is not free; the buyer pays for it in advance, whether the risk occurs or not. And if the seller underestimates and starts losing money, quality, relationships and even delivery can suffer.

The art of contracting is to put each risk with the party best able to manage it, at a fair price. That depends mostly on how clearly the scope can be described.

Clear, stable scope → fixed price. Uncertain or changing scope → cost-reimbursable or time and materials.

3See it in one picture: who carries the cost risk?

Who carries the cost risk?Buyer carriesmost riskSeller carriesmost riskFFPFPIFFP-EPAT&MCPIFCPAFCPFFScope clear and stable → fixed price (right)Scope uncertain → cost-reimbursable (left)
Moving right, the seller carries more of the cost risk and the buyer needs a clearer scope. Moving left, the buyer carries more risk and needs more oversight.

4How it looks on the exam

Exam-style question 1. A city needs a consultant to investigate the cause of repeated failures in a water treatment process. Nobody knows how long the investigation will take or what it will find. Which contract type is most appropriate?
A. Firm fixed price, to protect the city's budget
B. Cost-reimbursable, with an incentive or award fee
C. Fixed price with economic price adjustment
D. Fixed price incentive fee with a low ceiling price
Show the answer and the decode
Answer: B.
What it means
Highly uncertain scope and duration.
What is the question really asking?
The contract type that fits uncertain work.
Key words / trigger
“nobody knows how long … or what it will find”
PMP logic
When scope cannot be defined, a fixed price is either impossible or very expensive. Cost-reimbursable contracts fit; an incentive or award fee encourages efficiency. T&M with a not-to-exceed cap could also work for a small investigation.
Why the wrong answer looks attractive
A: a seller cannot price unknown work fairly; expect a huge risk premium or refusal. C: the adjustment is for price indexes, not unknown scope. D: still requires a defined scope, and a low ceiling invites disputes.

5Remember this

Your memory card

  • Contract type = who carries cost risk; clear scope → fixed price, uncertain scope → cost-reimbursable or T&M
  • Fixed price: seller carries most risk (FFP, FPIF, FP-EPA)
  • Cost-reimbursable: buyer carries most risk (CPFF, CPIF, CPAF); needs oversight
  • T&M: fixed rates, open total; use a not-to-exceed cap
  • Share ratio is buyer/seller; final fee = target fee + seller share × (target cost − actual cost)
  • PTA = (ceiling − target price) ÷ buyer share + target cost; above it, the seller pays all
  • Changes follow the contract's formal procedure
  • Agile: fixed budget/variable scope, price per iteration, capped T&M
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (Family 1: fixed-price contracts, Family 2: cost-reimbursable contracts, Family 3: time and materials, Incentive fees: how the share ratio works, FPIF and the point of total assumption, Choosing a contract type, What every contract contains, Contracts for agile work, Common misunderstandings, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
  • an interactive calculator
Open the full lesson → Create a free account