PMP lesson · People & Team Leadership · Building the team · lesson 6 of 6 · about 6 minutes

Training, skills gaps and knowledge transfer

All approachesFree preview
Goal: After this lesson you can find skills gaps early, plan training as part of resource management, and protect the project from single points of knowledge.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

Four weeks' notice

The robot cell uses a PLC platform nobody on the team has used before. The sponsor says: “They're good engineers; they'll learn on the job.”

Then Ana, the only person who knows the safety PLC, announces she is leaving in four weeks. Nobody else understands her work.

Skills are a resource like money and time. They must be planned, and knowledge must not live in one person's head.

2Plan skills like any other resource

During resource planning, compare the skills needed with the skills available. Gaps are risks. Close them with training, mentoring, pairing or hiring, and include the time and cost in the plan.

“Learn on the job” for a critical, unfamiliar technology is a risk, not a plan. Assess the gap and propose a targeted approach.

3A skills matrix shows the gaps

SkillAnaBenChenDmitriEva
New PLC platform✔✔––✔–
Vision system✔✔✔–––
Safety PLC✔✔––––
Robot programming–✔✔✔✔✔✔

✔✔ expert · ✔ can work with help · – none. The safety PLC row shows a single point of failure: if Ana leaves or is sick, nobody can do it.

One look shows where the project is fragile.

4How it looks on the exam

Exam-style question 1. The project will use a PLC platform none of the six controls engineers has used. The schedule is tight, and the sponsor suggests the engineers 'learn on the job'. What should the project manager do?
A. Accept the suggestion
B. Assess the skills gap and its risk, then propose a training approach, such as targeted training with vendor mentoring, in the resource management plan
C. Replace the team with contractors
D. Delay development until all engineers complete a long course
Show the answer and the decode
Answer: B.
What it means
A critical skills gap and a sponsor who wants to skip training.
What is the question really asking?
The right action.
Key words / trigger
“none of the six … has used”
PMP logic
Skills gaps are identified and closed in planning; a targeted approach balances risk and schedule.
Why the wrong answer looks attractive
A long delay seems safe, but a targeted approach manages the risk with less impact.

5Remember this

Your memory card

  • Skills are a resource: compare needed vs available in planning
  • Close gaps: training, mentoring, pairing; include time and cost
  • Avoid single points of knowledge; spread knowledge continuously
  • Departure → prioritised transfer now, by working together
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (Avoid single points of knowledge)
  • a worked example
  • the common traps (wrong vs right)
  • 2 exam-style questions with the decode
  • a 3-question quick check
Open the full lesson → Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.