Case study 1: the robot cell project (predictive / hybrid)
Predictive and hybridFree preview
Goal: After this case you can work through a multi-exhibit question set the way the 2026 exam presents it: read the questions, find the right exhibit, apply the concept.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
1The situation
The situation
You are the project manager for an eight-month robot cell project for a packaging customer. The hardware follows a predictive plan with FAT and SAT milestones; the HMI software is developed in sprints.
It is month 6. You have four exhibits on your desk: the earned value report, an email from the customer, an extract from the risk register and this week's site update.
Answer the four exam questions below, using the exhibits. Each question depends mainly on one exhibit.
2How to work through a case study
Read the questions first, then the exhibits. You'll know what to look for.
One fact per question: each question usually depends on one exhibit. Find it; ignore the rest.
Watch the numbers: write the key values down (PV, EV, AC, dates).
Apply the PMI mindset: assess before acting, follow the process, collaborate, be honest.
In the 2026 exam, case studies combine several exhibits (emails, tables, charts) with several questions. Read the questions first.
3The exhibits
Exhibit A · Earned value report (month 6)
BAC
$1,200,000
PV
$600,000
EV
$540,000
AC
$630,000
Note: the overrun comes mainly from repeated rework on welded frames; the cause has not been removed.
Exhibit B · Email from the customer
From: Operations Director Subject: One more thing
Given our long relationship, please add an automatic label-printing station to the cell as a goodwill gesture. It should be easy for your team. We need it at go-live.