Home › PMP lessons › Cost & EVM

PMP lesson · Cost & EVM · Cost: estimating, budget and earned value · lesson 2 of 5 · about 25 minutes

Cost baseline, budget and reserves

Predictive · hybrid programsFree preview
Goal: After this lesson you can build a cost baseline and project budget from estimates and reserves, explain who controls contingency and management reserve and how each is used, draw a time-phased baseline (S-curve), and reconcile planned spending with funding limits.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“How much money do you need, and when?”

The city has approved the renovation of a public library branch. Your team has estimated every work package: demolition, electrical, accessibility upgrades, shelving, IT and furniture. Together they add up to $90,000.

The risk register lists several identified risks, such as asbestos found behind old walls and late delivery of accessible doors. Their expected cost is about $8,000. The finance department also wants a small amount set aside for problems nobody has thought of.

Then the city's budget officer adds a constraint: “We can release at most $40,000 in the first quarter. The rest comes in the second quarter.” Your plan spends $48,000 in the first three months.

This lesson shows how to turn estimates into a cost baseline and a budget, what each reserve is for and who may use it, and how to adjust the plan when the money arrives more slowly than the work.

2From estimates to budget

Estimating answers “how much will each part cost?”. Determining the budget answers “how much do we authorize in total, and when will it be spent?”. Its main output is the cost baseline: the approved, time-phased budget against which performance is measured.

The budget is built by cost aggregation: activity estimates are added into work package estimates, work packages into control accounts, and control accounts into the project total. Reserves are then added at the right levels (see the table in the Picture section).

This structure matters. It lets the project manager see cost performance at each level, and it connects the money to the scope (WBS) and the schedule, which is the basis for earned value management in the next lessons.

Activities → work packages → control accounts → + contingency = cost baseline → + management reserve = project budget.

3See it in one picture: the S-curve and the funding limit

Cost baseline S-curve and funding limit0k25k50k75k100k012345648k > 40k limitBaseline $98kFundingMonth
Blue: the cost baseline accumulating over six months to $98,000 (BAC). Green steps: money the city releases. In month 3 planned spending ($48,000) is above the first-quarter funding ($40,000), so the plan must be reconciled.

4How it looks on the exam

Exam-style question 1. The work package estimates for a project total $450,000. The contingency reserve is $40,000 and the management reserve is $25,000. What is the budget at completion (BAC)?
A. $450,000
B. $515,000
C. $490,000
D. $475,000
Show the answer and the decode
Answer: C.
What it means
Estimates plus two reserves.
What is the question really asking?
BAC, the total of the cost baseline.
Key words / trigger
“budget at completion”
PMP logic
BAC = estimates + contingency = 450,000 + 40,000 = $490,000. The project budget, including management reserve, would be $515,000.
Why the wrong answer looks attractive
A: leaves out contingency, which is part of the baseline. B: that is the project budget, which includes management reserve. D: wrongly uses management reserve instead of contingency.

5Remember this

Your memory card

  • Activities → work packages → control accounts → + contingency = cost baseline (BAC) → + management reserve = project budget
  • Contingency: identified risks, inside the baseline, used by the PM as planned
  • Management reserve: unidentified risks, outside the baseline, needs approval; when used, BAC increases
  • Baseline changes only through change control; never rebaseline to hide variances
  • Time-phased baseline = S-curve = planned value (PV) over time
  • Funding limit exceeded → reconcile by rescheduling work with float
  • Agile: fixed cost per iteration, variable scope, track burn rate
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (What goes into the estimates, Control accounts, Two kinds of reserve, The cost baseline and BAC, Time-phasing and the S-curve, Funding requirements and funding limits, Using the reserves, Rebaselining, Budgeting in agile and hybrid projects, Common mistakes, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
  • an interactive calculator
Open the full lesson → Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.