“How much money do you need, and when?”
The city has approved the renovation of a public library branch. Your team has estimated every work package: demolition, electrical, accessibility upgrades, shelving, IT and furniture. Together they add up to $90,000.
The risk register lists several identified risks, such as asbestos found behind old walls and late delivery of accessible doors. Their expected cost is about $8,000. The finance department also wants a small amount set aside for problems nobody has thought of.
Then the city's budget officer adds a constraint: “We can release at most $40,000 in the first quarter. The rest comes in the second quarter.” Your plan spends $48,000 in the first three months.
This lesson shows how to turn estimates into a cost baseline and a budget, what each reserve is for and who may use it, and how to adjust the plan when the money arrives more slowly than the work.