What will it cost in the end?
Back to the robot cell. At week 5: BAC $100,000, PV $50,000, EV $40,000, AC $60,000. CPI = 0.67, SPI = 0.80.
The sponsor now asks a different question: “OK, we are over budget. So what will the final cost be?”
The honest answer is: it depends on why we are over budget. If the team keeps working the same way, the final cost will be very different from a case where the overrun was one bad supplier batch that is already fixed. Earned value gives you a formula for each story.