Forecasting with earned value: EAC, ETC and VAC

Predictive · also used in hybrid reportingFree preview
Goal: After this lesson you can calculate EAC, ETC and VAC, choose the right EAC formula from the cause of the variance, show why BAC ÷ CPI and AC + (BAC − EV) ÷ CPI are the same forecast, and present a forecast as a range that supports a decision.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“So what will it cost in the end?”

A city utility is replacing 1,000 old water meters at a budgeted $100 each: BAC = $100,000. By the status date, 500 meters should have been installed (PV = $50,000). Only 400 are done (EV = $40,000), and the work has cost $60,000 (AC).

The utility director asks the obvious question: “So what will the whole job cost?” You already know the CPI (0.67) and SPI (0.80) from the previous lesson. But they describe the past. The director needs the future.

The answer depends on why the project is over budget. If a crew damaged a delivery once, the rest may go to plan. If each meter simply takes longer than estimated, the overrun will continue. If old pipes need new fittings that nobody budgeted for, the original estimate is no longer valid.

This lesson shows how to turn earned value data into a forecast, how to choose the right formula for the right cause, and how to present the result honestly.

2Why forecast, and what the terms mean

Variances and indexes tell you how the project has performed so far. Sponsors make decisions about the future: approve more money, reduce scope, stop the project. Forecasting turns performance data into an expected final result, early enough to act.

Three forecast measures are used everywhere:

EAC
Estimate at completion
The expected total cost of the project when it is finished.
ETC
Estimate to complete
The expected cost of the remaining work, from now to the end.
VAC
Variance at completion
BAC − EAC: how far over (negative) or under (positive) budget the project will end.

These are linked by one identity that is always true: EAC = AC + ETC. What you have spent, plus what you still expect to spend. Every EAC formula is just a different way to estimate the ETC.

EAC = AC + ETC, always. ETC = EAC − AC. VAC = BAC − EAC (negative = overrun).

3See it in one picture: one project, four forecasts

Four forecasts compared with the budget0k50kBAC150k120kOne-time155kBottom-up150kCPI continues172.5kCPI × SPIEstimate at completion by assumption
The same EV data (BAC $100k, EV $40k, AC $60k, CPI 2/3, SPI 0.8) gives four different forecasts. The right one depends on the cause of the variance, not on the numbers.

4How it looks on the exam

Exam-style question 1. A project has a BAC of $200,000. Earned value is $80,000 and actual cost is $100,000. The overrun was caused by a one-time equipment failure that has been repaired, and the rest of the work is expected to proceed as planned. What is the estimate at completion?
A. $250,000
B. $200,000
C. $220,000
D. $240,000
Show the answer and the decode
Answer: C.
What it means
Over budget because of a one-time event that will not recur.
What is the question really asking?
EAC for an atypical variance.
Key words / trigger
“one-time equipment failure … proceed as planned”
PMP logic
EAC = AC + (BAC − EV) = 100,000 + 120,000 = $220,000. If the cause were continuing, BAC ÷ CPI = 200,000 ÷ 0.8 = $250,000.
Why the wrong answer looks attractive
A: uses BAC ÷ CPI, which assumes the problem continues. B: ignores the overrun already incurred. D: adds AC to BAC minus a wrong amount; it has no basis.

5Remember this

Your memory card

  • EAC = AC + ETC always; VAC = BAC − EAC (negative = overrun)
  • Remaining work at budget = BAC − EV; the question is at what efficiency it will be done
  • One-time cause → EAC = AC + (BAC − EV)
  • Continuing cause → EAC = BAC ÷ CPI (= AC + (BAC − EV) ÷ CPI)
  • Schedule must still be met → EAC = AC + (BAC − EV) ÷ (CPI × SPI)
  • Original estimate wrong → EAC = AC + bottom-up ETC
  • Present a range, the cause and options; BAC changes only through change control

📘 Quick reference: Study guide: EAC formulas: which one to use · Practice more PMP questions

The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (The key question: will past performance continue?, Formula 1: the problem was a one-time event, Formula 2: current cost performance will continue, Why BAC ÷ CPI makes sense: a short derivation, Formula 3: cost and schedule performance both affect the rest, Formula 4: the original estimate was wrong, Choosing the formula, Presenting forecasts and acting on them, Forecasting the finish date, Forecasting in agile projects, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
  • an interactive calculator