Home › PMP lessons › Cost & EVM

PMP lesson · Cost & EVM · Cost: estimating, budget and earned value · lesson 5 of 5 · about 25 minutes

TCPI and reading performance reports

Predictive · also used in hybrid reportingFree preview
Goal: After this lesson you can calculate the to-complete performance index for a budget or a forecast target, judge whether a recovery target is realistic, read an earned value performance report including trends and thresholds, and turn it into a clear recommendation.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“The team says it can still finish on budget”

Back at the city water-meter program: BAC $100,000, EV $40,000, AC $60,000. The forecast from the last lesson is about $150,000. The installation supervisor is confident: “We had a bad start. We will be faster now and still finish within $100,000.”

Is that realistic? Only $40,000 of budget is left, and $60,000 of work remains. To finish on budget, the crews must do $60,000 of planned work for $40,000 of real cost. That means working 50% more efficiently than planned, after working 33% less efficiently than planned so far.

The to-complete performance index (TCPI) turns this argument into one number. Together with the indicators you already know, it lets you read a performance report and test any promise of recovery.

This lesson teaches TCPI, then shows how to read a complete performance report: which numbers matter, how to see trends, and how to turn data into a recommendation.

2What TCPI measures

CPI looks back: how efficiently have we worked so far? TCPI looks forward: how efficiently must we work from now on to hit a cost target?

It compares the work remaining (in budget terms) with the money remaining to do it. If there is less money left than work left, the remaining work must be done more efficiently than planned, and TCPI is above 1.0.

To meet the original budget
TCPI = (BAC − EV) ÷ (BAC − AC)
(100,000 − 40,000) ÷ (100,000 − 60,000) = 60,000 ÷ 40,000 = 1.50.
To meet a new forecast (EAC)
TCPI = (BAC − EV) ÷ (EAC − AC)
(100,000 − 40,000) ÷ (150,000 − 60,000) = 60,000 ÷ 90,000 = 0.67.

The top of the fraction is always the same: work remaining. The bottom is the money you allow for it: what is left of the budget, or what is left of a new forecast.

TCPI = work remaining ÷ money remaining. Above 1.0 = must work better than planned; below 1.0 = can work worse than planned.

3See it in one picture: efficiency achieved vs efficiency needed

Efficiency achieved vs efficiency needed0.67CPI sofar1.50TCPI tomeet BAC0.67TCPI tomeet EAC $150k1.0 = on plan
The crews have achieved 0.67. Finishing within the original $100,000 would need 1.50 for the rest of the program: not credible. Finishing at the $150,000 forecast needs exactly today's performance.

4How it looks on the exam

Exam-style question 1. A project has a BAC of $500,000, an earned value of $300,000 and an actual cost of $350,000. The sponsor insists that the project must finish within the original budget. What efficiency must the remaining work achieve?
A. 0.86
B. 1.33
C. 1.17
D. 0.75
Show the answer and the decode
Answer: B.
What it means
Behind on cost, sponsor wants to keep BAC.
What is the question really asking?
TCPI to meet BAC.
Key words / trigger
“finish within the original budget”
PMP logic
TCPI = (500,000 − 300,000) ÷ (500,000 − 350,000) = 200,000 ÷ 150,000 = 1.33. CPI so far is 300 ÷ 350 = 0.86, so this would need a large improvement.
Why the wrong answer looks attractive
A: that is the current CPI, not the required efficiency. C: inverts AC and EV (350 ÷ 300). D: inverts the TCPI fraction (150 ÷ 200).

5Remember this

Your memory card

  • TCPI = work remaining ÷ money remaining = (BAC − EV) ÷ (BAC − AC), or ÷ (EAC − AC) for a new target
  • TCPI above 1.0 = must work better than planned; compare it with CPI
  • TCPI more than about 0.05–0.10 above CPI → target unrealistic without a real change
  • AC ≥ BAC with work left → meeting BAC is impossible; use an EAC
  • Data → information → reports; a report gives status, cause, forecast, options, recommendation
  • Watch trends over several periods; act before thresholds are crossed
  • Report bad news early and honestly (PMI Code of Ethics)
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (Reading TCPI against CPI, Special cases worth understanding, A second example: the hospital project, The performance reporting chain, Status, progress and forecast, Trends matter more than snapshots, Variance analysis: from numbers to causes, Writing the recommendation, Honest reporting, Agile and hybrid reporting, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
  • an interactive calculator
Open the full lesson → Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.