The PMO and project governance

All approaches (tailored for agile and hybrid)Free preview
Goal: After this lesson you can describe the three types of PMO, explain phase gates, tolerances and approval thresholds, and tailor governance instead of bypassing it.

1The situation

“This template is a waste of time”

The PMO requires every project, including agile ones, to submit a 40-page design document before development starts. The robot cell's software team says it is wasteful and proposes to simply ignore it.

Meanwhile, a phase gate is coming: the project meets three of five criteria, and the sponsor wants to “present it positively”.

Governance can feel like bureaucracy. But it exists to protect the organisation's money and decisions, and the PMP expects you to work with it.

2Three types of PMO

A project management office standardises project governance and shares resources, methods and tools. Its level of control varies:

Supportive
Low control
Templates, training, lessons learned.
Controlling
Moderate control
Requires compliance with methods and reporting.
Directive
High control
Directly manages the projects.

3Three types of PMO

Supportive PMO

Low control. Provides templates, training, lessons learned, best practices. Like a consultant.

Controlling PMO

Moderate control. Requires compliance: frameworks, templates, reporting, audits.

Directive PMO

High control. Directly manages projects; PMs report to the PMO.
From advisor (supportive) to manager (directive).

4How it looks on the exam

Exam-style question 1. The PMO requires a 40-page detailed design document from every project, including agile ones. The agile team considers it wasteful and proposes ignoring it. What should the project manager do?
A. Support the team and ignore the requirement
B. Insist on the full document
C. Produce the document personally
D. Engage the PMO to understand the purpose and propose a tailored alternative that meets the governance need
Show the answer and the decode
Answer: D.
In simple English
A governance rule that doesn't fit the delivery approach.
What is the question really asking?
The right action.
Key words / trigger
“proposes ignoring it”
PMP logic
Tailor governance with the governance body; meet its intent without waste.
Why the wrong answer looks attractive
Agile values seem to support ignoring it, but bypassing governance is never the PMP answer.

5Remember this

Your memory card

  • PMO types: supportive (advise) · controlling (require) · directive (manage)
  • Governance: gates, tolerances, thresholds, steering
  • Inside tolerance → act; outside → escalate promptly with options
  • Rule doesn't fit? Tailor with agreement; never ignore or circumvent
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (Governance)
  • a worked example
  • the common traps (wrong vs right)
  • 2 exam-style questions with the decode