PMP lesson · Project Initiation & Business Value · The organisation around the project · lesson 4 of 4 · about 6 minutes
Project roles and the RACI chart
All approachesFree preview
Goal: After this lesson you can describe the main project roles, especially the sponsor's, and build a RACI chart with exactly one accountable person per activity.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
On the robot cell, the HMI alarm list has been “nearly finished” for three weeks. The controls lead thinks the customer owns it. The customer thinks the integrator owns it. The PM thought both were working on it together.
When everyone is a little responsible, nobody is. A simple chart would have shown, on day one, who does the work and who owns the result.
2Key roles
The exam often asks whose job something is:
Sponsor
Authority and funding
Issues the charter, champions the project, decides beyond the PM's authority, owns the business case.
PM
Delivery
Leads the team to the objectives; owns the management of the project.
Product owner
Value (agile)
Owns the backlog: what and in which order.
3Roles at a glance
Sponsor
Provides funding and authority; issues the charter; champions the project; decides beyond the PM's authority; owns the business case.
Project manager
Leads the team to deliver the objectives; plans, coordinates, communicates, manages risks and changes.
Functional manager
Owns people and technical standards in a department; negotiates resources with the PM.
Does the work; estimates it; in agile, decides how.
Product owner (agile)
Owns the backlog and value; decides what and in which order.
Each role has a clear focus.
4How it looks on the exam
Exam-style question 1. Ownership of an important deliverable is unclear; two team leads each believe the other is responsible, and work has stalled. What would MOST likely have prevented this?
A. A more detailed Gantt chart
B. A responsibility assignment matrix (RACI) with one accountable person for each deliverable
C. More frequent status meetings
D. A larger contingency reserve
Show the answer and the decode
Answer: B.
What it means
Unclear ownership caused a stall.
What is the question really asking?
What would prevent it.
Key words / trigger
“each believe the other is responsible”
PMP logic
A RACI with exactly one 'A' per deliverable makes ownership explicit.
Why the wrong answer looks attractive
A Gantt chart shows timing, not ownership.
5Remember this
Your memory card
Sponsor: funding, authority, charter, business case · PM: delivery
Product owner: backlog and value (agile)
RACI: R does · A owns (only one) · C input before · I told after