Kanban and WIP limits

Agile, especially support and maintenanceFree preview
Goal: After this lesson you can explain the origins and principles of the Kanban method, design a board with explicit policies and WIP limits, explain why a pull system improves flow, choose classes of service, compare Kanban with Scrum, and decide when Kanban fits.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“Everything is urgent, and nothing gets finished”

A regional power utility runs an IT team that supports its customer portal: outage maps, bill payments, meter readings. Requests arrive every day from customers, call-center staff and managers. Each one seems urgent, so the team starts each request as soon as it arrives.

After a few months, the board shows more than 40 open items. Developers switch between five tasks a day. Even simple fixes take weeks because they wait behind half-finished work. The team tried two-week sprints, but urgent outage-related fixes could not wait for the next sprint.

The team adopts Kanban. It makes all work visible, limits how many items can be in each stage at once, and pulls new work only when there is capacity. Within two months, the average lead time drops by more than half, and nobody has to work longer hours to achieve it.

This lesson explains the Kanban method step by step: where it comes from, its principles and practices, how to set WIP limits, how classes of service handle urgency, and how it compares with Scrum.

2Where Kanban comes from

Kanban means “signboard” or “visual card” in Japanese. At Toyota in the 1950s, Taiichi Ohno used kanban cards to signal when a workstation needed more parts. Production was pulled by real demand instead of being pushed by a schedule, which kept inventory low and exposed problems quickly. This became a core part of the Toyota Production System and of Lean thinking.

In the 2000s, David J. Anderson adapted these ideas to knowledge work, first at Microsoft and then at Corbis, creating the Kanban Method. Instead of physical parts, the “inventory” is unfinished work: requests, features, fixes. The goal is the same: smooth, predictable flow of value.

3See it in one picture: a board with WIP limits

A Kanban board with WIP limitsOptionsWIP —AnalyzeWIP 3DevelopWIP 4TestWIP 3DoneWIP —Test is full (3/3)Pull, don't push: work moves only when the next column has space
Each column has a WIP limit. Test is full, so Developers cannot push more work into it; they help testing or pull other work that does not add to the queue. This is how a pull system exposes and relieves bottlenecks.

4How it looks on the exam

Exam-style question 1. A maintenance team receives unpredictable requests every day, many of which cannot wait two weeks. The team wants an agile approach. Which approach fits best?
A. Scrum with four-week sprints to batch requests
B. Kanban with WIP limits and service classes
C. A predictive plan with a monthly change board
D. Scrum with requests added mid-sprint as they arrive
Show the answer and the decode
Answer: B.
What it means
Unpredictable, urgent, interrupt-driven work.
What is the question really asking?
The fitting approach.
Key words / trigger
“cannot wait two weeks”
PMP logic
Kanban handles continuous, unpredictable flow; classes of service manage urgency; WIP limits keep lead times short. For product development with clear sprint goals, Scrum would fit better.
Why the wrong answer looks attractive
A: long sprints delay urgent work. C: a monthly board is too slow. D: constantly changing sprint scope undermines Scrum's Sprint Goal.

5Remember this

Your memory card

  • Kanban: from Toyota (Ohno); adapted to knowledge work by David Anderson
  • Practices: visualize, limit WIP, manage flow, explicit policies, feedback loops, improve experimentally
  • Starts with what you do now; no required roles or sprints
  • WIP limits + pull → shorter lead times (Little's Law), less switching, visible bottlenecks
  • Column full → stop starting; help finish
  • Classes of service handle urgency; strictly limit expedite items
  • Kanban fits unpredictable service work; Scrum fits goal-driven product work; Scrumban combines them
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (The Kanban Method: principles, The six core practices, Designing the board, WIP limits, Pull, don't push, Classes of service: handling urgency, Cadences: the feedback loops, Kanban versus Scrum, Measuring a Kanban system, Kanban in predictive and hybrid settings, Common mistakes, How PMI tests Kanban, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
  • an interactive calculator
Open the full lesson → Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.