Story points and relative estimation

Agile and hybridFree preview
Goal: After this lesson you can explain why agile teams estimate relatively, what a story point represents, how to run planning poker and affinity estimation, why the Fibonacci-like scale is used, and how to avoid the common mistakes of converting points to hours or using them to compare teams.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“How many hours will that take?”

The transit app's Developers are asked to estimate a new feature: showing real-time bus arrivals on the trip screen. The Product Owner wants a number in hours. One Developer says 6 hours, another says three days. Both are guessing, and both know it.

Then the Scrum Master asks a different question: “Compared with ‘view stop timetable’, which we all know took about a week, is this smaller, about the same, or bigger?” Within a minute, everyone agrees it is bigger, maybe two or three times as big.

People are poor at predicting absolute durations but surprisingly good at comparing sizes. That is the idea behind story points: estimate how big work is relative to other work, then let the team's measured velocity translate size into time.

This lesson explains, step by step and with the transit team, what story points measure, why the scale looks the way it does, how planning poker and affinity estimation work, and how to keep points useful instead of turning them into a source of conflict.

2Absolute versus relative estimation

Absolute estimation asks “how long will this take?” in hours or days. Relative estimation asks “how big is this compared with something we know?” Research on human judgment shows that people are much better at the second question. We can tell that one building is about twice as tall as another long before we can say how many meters tall either is.

Relative estimation also avoids a hidden problem of hours: different people work at different speeds. An expert may need 4 hours for a task a newcomer needs 12. Story points describe the work, not the person, so the team can agree on a size even when their personal speeds differ.

3See it in one picture: the point scale

The story point scale12358132040100fits in a sprintsplit soonepic: split firstGaps grow with size, because uncertainty grows with sizeReference story “view stop timetable” = 3 points
The modified Fibonacci scale. Green values usually fit in a sprint; 13 should be split soon; 20 and above are epics that must be split before planning.

4How it looks on the exam

Exam-style question 1. During planning poker, four developers show 2, 3, 3 and 13 for the same story. What should happen next?
A. Use the average of the four cards, 5, as the estimate
B. Accept 13 to be safe, since it is the highest card
C. Those who chose 2 and 13 explain their thinking
D. Accept 3, since most of the developers chose it
Show the answer and the decode
Answer: C.
What it means
A wide spread of estimates.
What is the question really asking?
The next step in planning poker.
Key words / trigger
“2, 3, 3 and 13”
PMP logic
The extremes explain their reasoning, which usually reveals different assumptions; then the team re-votes. If all had shown 3, the team would simply accept 3.
Why the wrong answer looks attractive
A: averaging hides the misunderstanding. B: padding to the highest number distorts forecasts. D: majority voting skips the conversation that reveals risks.

5Remember this

Your memory card

  • Relative estimation: compare with known work; people are better at comparing than predicting
  • Story point = effort + complexity + uncertainty, on the team's own scale with reference stories
  • Fibonacci-like scale: gaps grow with size and uncertainty; 13+ should be split
  • Planning poker: simultaneous reveal (no anchoring), extremes explain, re-vote
  • Developers estimate; the PO explains; affinity estimation sizes many items fast
  • Time and cost come from velocity, not from converting points to hours
  • Never compare teams by points; never set velocity targets (point inflation)
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (What a story point represents, Why the Fibonacci-like scale, Planning poker, Who estimates, Estimating many items quickly: affinity estimation, Other relative scales, From points to dates and costs, Why not convert points to hours, Estimating bugs, spikes and technical work, Keeping estimates consistent over time, Common mistakes, Estimation in the PMP exam, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
Open the full lesson → Create a free account