Velocity and capacity: measuring and forecasting team throughput

Agile and hybridFree preview
Goal: After this lesson you can calculate velocity and its range from past sprints, adjust a sprint forecast for team capacity, explain what changes velocity and why it stabilizes, and recognize the common misuses of velocity as a performance target.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“Last sprint you did 34 points. Do 40 this time.”

A software team of six Developers is building an online appointment-booking system for a chain of physiotherapy clinics. They work in two-week sprints. Over the last six sprints they completed 18, 26, 31, 30, 34 and 32 story points.

At the start of sprint planning, a department manager drops in: “You did 34 points two sprints ago. Let's aim for 40 this sprint. And by the way, the mobile team next door does 50 points a sprint. Why are you slower?”

Meanwhile, one Developer is going on vacation for a week, and Monday is a statutory holiday. The Product Owner wants to know how much the team can realistically take on.

This lesson explains, step by step, what velocity really measures, how to turn it into a sensible forecast using capacity, why the manager's two requests are both mistakes, and how velocity is used (and misused) in practice.

2What velocity is

Velocity is the amount of work a team completes in one iteration, measured in the same unit the team uses to size its backlog, usually story points. It is a measure of the team's historical throughput, used mainly for forecasting.

Only work that meets the Definition of Done counts. A story that is 90% finished at the end of a sprint earns zero points in that sprint. This rule keeps velocity honest: partial work is not value, and estimating “percent done” for knowledge work is unreliable.

Velocity is not part of the Scrum Guide. Scrum asks the team to consider its past performance and its capacity in sprint planning; velocity is one common way to do that. Kanban teams measure throughput in items per week instead (see the flow metrics lesson).

Velocity = story points of items that met the Definition of Done in the iteration. No partial credit.

3See it in one picture: velocity settles, then forecasts

Velocity over six sprints01020304018S126S231S330S434S532S6Last 3 average: 32 · range 30–34 (green band)new team settlingStory points completed (Done) per sprint
The first two sprints (grey) are low while the new team settles. From sprint 3, velocity is stable: average of the last three sprints = 32, range 30–34 (green band). Use that, not the best single sprint, to forecast.

4How it looks on the exam

Exam-style question 1. A team completed 24, 30, 27 and 29 story points in its last four sprints. The Product Owner asks how many points to plan for the next sprint, under normal conditions. What is the best answer?
A. About 30, the best recent result
B. About 28, the average of recent sprints
C. About 24, the lowest result, to be safe
D. About 110, the total of the four sprints
Show the answer and the decode
Answer: B.
What it means
Four stable sprints, normal capacity.
What is the question really asking?
A reasonable velocity forecast.
Key words / trigger
“under normal conditions”
PMP logic
Average = (24 + 30 + 27 + 29) ÷ 4 = 27.5 ≈ 28, with a range of 24–30. If capacity were reduced, the forecast would be scaled down. For a high-confidence commitment, the low end of the range could be used.
Why the wrong answer looks attractive
A: the best sprint overstates normal performance. C: the lowest value is overly cautious for normal planning. D: the total of four sprints, not a per-sprint figure.

5Remember this

Your memory card

  • Velocity = points of Done items per iteration; no partial credit
  • Story points are relative and team-specific
  • Forecast with the average of the last 3–5 sprints, and keep the range (yesterday's weather)
  • Adjust for capacity: velocity × (available ÷ normal capacity)
  • The Developers decide how much to take on; velocity is a forecast, not a promise
  • Not a target (Goodhart's law), not for comparing teams, not a measure of value
  • New teams stabilize after a few sprints; team or DoD changes reset velocity
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (Why story points, and why they are relative, Average and range: “yesterday's weather”, Capacity: how much time the team really has, Focus factor and why capacity is never 100%, Who decides how much to take on, Why velocity changes, and why it stabilizes, The misuses of velocity, Measuring velocity correctly in practice, Velocity in the retrospective, Alternatives and complements, Velocity in hybrid projects, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
Open the full lesson → Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.