Release planning: fixed date, variable scope

Agile and hybridFree preview
Goal: After this lesson you can build a release forecast from a prioritized backlog and a velocity range, explain what will, might and will not be delivered by a date, use MoSCoW and MVP thinking to shape scope, and update and communicate the plan every sprint.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“Will everything be ready for the spring campaign?”

The physiotherapy clinic chain plans a large spring marketing campaign. The new booking app must be live when the campaign starts, five sprints from now. The date cannot move: the advertising is already booked.

The Product Backlog for the release contains 210 story points: online booking, payment, appointment reminders, a waiting list, patient reviews, a loyalty program and a chat feature. The team's recent velocity ranges from 28 to 36 points per sprint.

The marketing director asks the classic question: “Will everything be ready?” A traditional plan would answer with one date for one fixed scope. An agile release plan answers differently: with the date fixed, it shows what will be ready, what might be ready, and what will not.

This lesson shows how to build that forecast, how to decide what goes first, and how to keep the plan honest as the release progresses.

2Releases, roadmaps and sprints

A sprint (iteration) produces a usable increment every few weeks. A release puts one or more increments into the hands of users, often after several sprints, sometimes after every sprint. A product roadmap shows the planned sequence of releases and goals over a longer period, usually several quarters.

Release planning connects these levels: which backlog items are expected in which release, and when. It is not a commitment to an exact feature list; it is a forecast that is updated as the team learns. In Scrum, the Product Owner is accountable for ordering the backlog and for decisions about releases.

3See it in one picture: what fits by the date

Release forecast: what will fit in five sprintsAll 210Must + Should 170Must 12001234536/sprint → 180dashed line: 28/sprint → 140Sprint
In five sprints the team will complete between 140 points (low velocity) and 180 points (high). Must-haves (120) fit even at the low velocity. Must + Should (170) fit only near the high end. All 210 points do not fit.

4How it looks on the exam

Exam-style question 1. A release must ship in 6 sprints. The team's recent velocity ranges from 20 to 26 points, and the ordered backlog holds 170 points. What should the Product Owner tell stakeholders?
A. All 170 points will be delivered if the team works harder
B. About 120 points will be delivered; up to 156 might be
C. Nothing can be forecast until the third sprint is complete
D. The release date must move so that all 170 points are delivered
Show the answer and the decode
Answer: B.
What it means
Fixed date, velocity range, backlog bigger than the forecast.
What is the question really asking?
An honest release forecast.
Key words / trigger
“must ship in 6 sprints”
PMP logic
Low: 20 × 6 = 120 (will be done). High: 26 × 6 = 156 (might be done). The last 14 points or more will not be done by the date. If the date were flexible, 170 ÷ 20 = 9 sprints at worst would be the forecast instead.
Why the wrong answer looks attractive
A: “working harder” is not a forecast and ignores the data. C: a range forecast is possible now and is updated each sprint. D: the date is fixed; agile adjusts scope, not the date.

5Remember this

Your memory card

  • Agile releases fix date and team; scope is the variable; quality (DoD) is never the variable
  • Forecast: low velocity × sprints = will be done; high × sprints = might be done; beyond = won't
  • Order the backlog by value; MoSCoW: Must-haves should fit the low forecast
  • MVP = smallest version to learn; MMF = smallest releasable piece of value
  • Burn-up charts show scope growth; burn-downs can hide it
  • Update and share the release plan every sprint, in terms of confidence
  • The Product Owner decides scope; the Developers provide the forecast
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (The inverted triangle: fix time and cost, flex scope, Inputs to a release plan, Forecasting with a velocity range, Planning a release before velocity exists, Ordering the backlog: MoSCoW and value, Minimum viable product and minimum marketable feature, Scope growth and the burn-up chart, Updating and communicating the plan, Release goal and sprint goals, Release planning in hybrid projects, Common mistakes, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
  • an interactive calculator
Open the full lesson → Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.