“Will everything be ready for the spring campaign?”
The physiotherapy clinic chain plans a large spring marketing campaign. The new booking app must be live when the campaign starts, five sprints from now. The date cannot move: the advertising is already booked.
The Product Backlog for the release contains 210 story points: online booking, payment, appointment reminders, a waiting list, patient reviews, a loyalty program and a chat feature. The team's recent velocity ranges from 28 to 36 points per sprint.
The marketing director asks the classic question: “Will everything be ready?” A traditional plan would answer with one date for one fixed scope. An agile release plan answers differently: with the date fixed, it shows what will be ready, what might be ready, and what will not.
This lesson shows how to build that forecast, how to decide what goes first, and how to keep the plan honest as the release progresses.