PMP lesson · Agile Practices · Value and risk in agile · lesson 1 of 2 · about 25 minutes
Spikes and the risk-adjusted backlog
Agile and hybridFree preview
Goal: After this lesson you can explain what a spike is and when to use one, design a timeboxed spike with a clear question and output, order a backlog by both value and risk, track risk with a risk burndown chart, and connect agile risk practices to formal risk management.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
1The situation
“We can't estimate it, we've never used that system”
The transit app must accept fare payments through a provider the agency signed a contract with last month. Nobody on the team has used its interface. In refinement, the Developers refuse to estimate the payment stories: “It could be three days or three weeks. We simply don't know.”
The Product Owner is worried. Payment is the most valuable feature of the next release, and the launch date is fixed. If the integration turns out to be difficult, the team needs to know now, not in the last sprint.
Agile teams have two tools for exactly this situation. A spike is a short, timeboxed piece of research that turns “we don't know” into “now we know enough to estimate and decide”. A risk-adjusted backlog deliberately moves risky, valuable work to the front, so that the team learns early while there is still time to change course.
This lesson explains both tools step by step, and shows how they connect to the risk management you studied in the risk lessons.
2What a spike is
A spike is a timeboxed investigation whose output is knowledge, not product functionality. The term comes from Extreme Programming: like a spike driven through all layers of a problem, it is a narrow, deep exploration to answer a specific question.
Typical questions, all of them concrete: Can our system connect to this payment provider? Which of two libraries performs better under load? How do users react to this kind of screen? The answer lets the team estimate, choose a design or decide whether to continue at all.
A spike is a backlog item like any other: the Product Owner orders it, and it is planned into a sprint. It simply produces a decision or an estimate instead of a feature.
Spike = timeboxed research item; output = knowledge that enables a decision or an estimate.
3See it in one picture: value and risk
Do valuable, risky work first so that the team learns early. Safe valuable work follows. Low-value work comes last; low-value, high-risk work is avoided.
4How it looks on the exam
Exam-style question 1. The team cannot estimate a story because it depends on an external interface that nobody has used. The story is highly valuable and needed for the next release. What should the team do?
A. Estimate it at the maximum size to be safe
B. Run a timeboxed spike to learn about the interface
C. Move the story to the bottom of the backlog
D. Ask the vendor to estimate the work for the team
Show the answer and the decode
Answer: B.
What it means
High value, high uncertainty, estimate blocked.
What is the question really asking?
The appropriate agile response.
Key words / trigger
“cannot estimate … nobody has used”
PMP logic
A timeboxed spike answers the specific question, after which the story can be estimated and planned. If the uncertainty were small, a normal estimate with a wider range would do.
Why the wrong answer looks attractive
A: padding hides the uncertainty and distorts the forecast. C: delaying risky, valuable work moves the risk to the end. D: the Developers must estimate their own work.
5Remember this
Your memory card
Spike = timeboxed research; output is knowledge for a decision or estimate (from XP)
Technical spikes explore technology; functional spikes explore product behavior or user response
Good spike: clear question, timebox, expected output, decision point; code is usually thrown away
Risk-adjusted backlog: high value + high risk first; avoid low value + high risk
Risks become backlog items: spikes, prototypes, load tests, early reviews
Risk burndown shows exposure falling; a long flat line is a warning
Same idea in predictive work: feasibility studies, proofs of concept, pilots
The full lesson in the PMCLEAR app also has:
the rest of the lesson (Technical and functional spikes, Designing a good spike, When to use a spike, and when not to, Spikes in planning and reviews, Spikes and velocity, Agile risk management: the idea, The risk-adjusted backlog, Turning risks into backlog items, Risk burndown charts, Linking agile risks to the formal risk register, Other techniques for early learning, Spikes and early learning in predictive and hybrid projects, Common mistakes, Glossary, Sources and further reading)
Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.