PMP lesson · Risk · Risk management · lesson 2 of 3 · about 30 minutes
Risk analysis: probability, impact, EMV and decision trees
All approaches (predictive, agile, hybrid)Free preview
Goal: After this lesson you can rank risks with a probability and impact matrix, calculate expected monetary value (EMV) with the correct signs, solve a decision tree, and explain what EMV can and cannot tell you about the contingency reserve.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
1The situation
Twenty risks, one sponsor, one big question
You manage the build-out of a new outpatient clinic in a leased building. Opening day is in nine months. In the risk workshop, the team identified 20 risks: a permit delay, a late X-ray unit, undocumented wiring, a fire-door certification, a possible furniture discount, and more.
You cannot give all 20 risks the same attention. Some are likely and expensive. Some are unlikely and cheap. A few are unlikely but dangerous.
Then the sponsor asks two questions: “Which risks should worry us most?” and “How much money should we keep aside for them?” A week later the architect adds a third: “Should we pay $200,000 extra for prefabricated modular exam rooms that could let us open earlier?”
This lesson gives you the tools to answer all three questions: qualitative analysis to rank the risks, expected monetary value to put a money value on uncertainty, and a decision tree to choose between options when the outcome is uncertain.
2Where risk analysis fits
Risk management is a cycle, not a single meeting. In predictive projects it usually follows this order: plan how risks will be managed → identify risks → analyze them (first qualitatively, then quantitatively if needed) → plan responses → implement the responses → monitor and repeat.
Analysis is the bridge between a long list of risks and a short list of actions. Its job is to answer two questions: which risks matter most? and how big is the uncertainty, in money or time?
The input is the risk register, where each risk is written as cause → event → effect and has an owner. The output is an updated register: each risk has a priority, and the most important ones may also have numbers (EMV, probability of meeting a date).
Exam order: identify → qualitative analysis → quantitative analysis (only when it adds value) → plan responses. You cannot plan good responses before you know which risks matter.
3See it in one picture: the decision tree
■ decision node (you choose)● chance node (uncertain)◀ end of path (final result)
Fold the tree back from right to left. Modular: 0.70 × $500k + 0.30 × $100k = $380k, minus the $200k cost = +$180k. Traditional: 0.80 × $0 + 0.20 × (−$150k) = −$30k. A risk-neutral organization chooses modular.
4How it looks on the exam
Exam-style question 1. The team has identified 35 risks for a new distribution center, and the sponsor wants to know which ones deserve the most attention before the steering meeting in three days. No risk has been analyzed yet. What should the project manager do?
A. Run a Monte Carlo simulation that includes all 35 identified risks
B. Develop and approve detailed response plans for all 35 risks
C. Rate each risk's probability and impact and rank them by priority
D. Transfer the highest-impact risks to suppliers through contract changes
Show the answer and the decode
Answer: C.
What it means
Many risks, nothing analyzed yet, little time, and the sponsor wants to know which matter most.
What is the question really asking?
The right next step to prioritize risks.
Key words / trigger
“which ones deserve the most attention · no risk has been analyzed yet”
PMP logic
Prioritizing risks is qualitative analysis: fast, applied to every risk, and done before quantitative analysis or response planning. Another answer could be right later: once the top risks are known, a Monte Carlo simulation could support a schedule or budget decision.
Why the wrong answer looks attractive
A: Monte Carlo is quantitative, slow, and normally comes after prioritization. B: responses for all 35 risks wastes effort on minor ones; planning responses comes after analysis. D: transfer is a response strategy; choosing responses before analysis skips a step, and transferring everything is rarely appropriate.
5Remember this
Your memory card
Qualitative analysis ranks every risk (probability × impact, defined scales); quantitative analysis puts numbers on the top risks or the whole project
EMV = probability × impact. Threats negative, opportunities positive. EMV is a long-run average; it almost never happens exactly
Outcomes on a chance node are alternatives: probabilities add up to 100%; never add the outcomes together
Decision tree: fold back from right to left; net EMV = expected value − option cost (subtract once); risk-neutral → best net EMV
Net EMV of the risks = a starting estimate for contingency reserve; few large or connected risks → simulation or confidence level (P80)
the rest of the lesson (Three words you need first, Qualitative analysis: rank every risk, Risk appetite, thresholds and the safety exception, Quantitative analysis: when it is worth it, Expected monetary value (EMV): what it really means, Two different uses of EMV, Decision trees, step by step, From EMV to contingency reserve, Monte Carlo simulation and sensitivity analysis, Limits of risk analysis, and the biases behind them, Risk analysis in agile and hybrid work, Glossary, Sources and further reading)
Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.