Dependencies, leads and lags: the logic behind every schedule

Predictive · hardware in hybrid projectsFree preview
Goal: After this lesson you can identify the four relationship types, classify any dependency as mandatory or discretionary and internal or external, apply leads and lags to calculate dates, and explain which dependencies can be changed to shorten a schedule.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“Why can't the painters start tomorrow?”

You are managing the renovation of a dental clinic. The owner wants to reopen as soon as possible and asks why the painters cannot start tomorrow, at the same time as the drywall crew.

The drywall crew explains that walls must be hung, taped and dry before anyone can paint. The electrician adds that the city inspector must approve the wiring before any wall is closed. The owner's office manager says the dentist prefers that no work is done during patient hours next door.

These are all dependencies, but they are not the same kind. Some are physics, some are law, some are preferences, and some depend on people outside your project. Some can be changed to save time; others cannot.

Before you can calculate a critical path (next lesson), you must get the logic right. This lesson teaches the vocabulary and the rules that every schedule is built on.

2Why schedule logic matters

A schedule is not a list of dates. It is a model: activities connected by dependencies. When one date changes, the model shows what else moves. If the logic is wrong or missing, the schedule looks fine on paper but fails in reality.

In the PMBOK process view, defining the logic is called sequencing activities. Its main output is the project schedule network diagram. Good sequencing is the foundation for the critical path, for float, and for every compression decision later.

Every activity, except the first and last, should have at least one predecessor and one successor. Activities with no links are “dangling” and hide real delays.

3See it in one picture: the four relationship types

The four dependency relationship typesFSfinish → startPredecessorSuccessorPaint after drywallSSstart → startPredecessorSuccessorCabling 2 days after framing startsFFfinish → finishPredecessorSuccessorTesting ends after coding endsSFstart → finishPredecessorSuccessorOld system runs until new one starts
Blue = predecessor, orange = successor, red arrow = the dependency. The arrow always runs from the controlling end of the predecessor to the controlled end of the successor.

4How it looks on the exam

Exam-style question 1. A new patient-records system is being tested. Final acceptance testing cannot be completed until data migration from the old system has been completed, but testing can begin earlier with sample data. Which relationship best describes the link between migration and acceptance testing?
A. Finish-to-start
B. Start-to-start
C. Start-to-finish
D. Finish-to-finish
Show the answer and the decode
Answer: D.
What it means
Testing can start before migration ends, but cannot finish until migration finishes.
What is the question really asking?
The relationship type.
Key words / trigger
“cannot be completed until … completed”
PMP logic
The finish of testing is controlled by the finish of migration: finish-to-finish. If testing could not start at all before migration ended, the answer would be finish-to-start.
Why the wrong answer looks attractive
A: FS would stop testing from starting early, which the scenario allows. B: SS links the starts, but the constraint here is on the finish. C: SF links the predecessor's start to the successor's finish, which does not fit.

5Remember this

Your memory card

  • Four relationship types: FS (most common), SS, FF and SF (rare: handovers and shifts)
  • Every dependency has two attributes: mandatory or discretionary, and internal or external
  • Fast tracking changes discretionary logic only; external dependencies are tracked as risks
  • Lag = waiting time, no resources; lead = overlap (negative lag); work with an owner = an activity
  • FS + lag: start after finish + lag · SS + lag: start after start + lag · FF + lag: finish after finish + lag
  • Several predecessors → take the latest date they allow
  • Use logic, not date constraints; constrain only real external dates
The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (Predecessor, successor and the precedence diagramming method, The four relationship types, Two attributes of every dependency, Why the classification matters, Leads and lags, Calculating dates with relationships, leads and lags, How dependencies are found, Constraints are not dependencies, Dependencies in agile and hybrid projects, Common mistakes and their causes, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
Open the full lesson → Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.