2Why the critical path matters
Every project has activities that can be delayed without hurting the end date, and activities that cannot. The critical path is the longest chain of dependent activities from start to finish. Its length is the shortest possible project duration.
Knowing it tells the project manager where to focus. A one-day slip on the critical path delays the whole project by one day. A one-day slip elsewhere may cost nothing. Without this knowledge, managers spread their attention evenly, or worse, put pressure on the wrong activities.
The method was developed in the late 1950s (DuPont and Remington Rand created CPM; the US Navy created PERT for the Polaris program at almost the same time). It remains the basis of every scheduling tool, from Microsoft Project to Primavera.
Critical path = the longest path through the network = the shortest time in which the project can be finished.
Reading a network diagram
A schedule network shows activities and the logic between them. In the activity-on-node (AON) format used by the PMP exam, each box (node) is an activity and each arrow is a dependency, usually finish-to-start: the next activity starts when the previous one finishes.
A path is any route from the start of the network to its end. Our office fit-out has three paths: A → B → D, A → C → D and E → D.
Two kinds of junction need special attention. A merge point is where several arrows come into one activity (D has three predecessors). A burst point is where one activity has several successors (A has two). These are exactly the places where the calculations need care.
The four dates of every activity
Early dates come from the forward pass (left to right). Late dates come from the backward pass (right to left). The difference between them is float.
ES
Early start
The earliest the activity can start, given its predecessors.
EF
Early finish
The earliest it can finish: ES + duration.
LS
Late start
The latest it can start without delaying the project end.
LF
Late finish
The latest it can finish without delaying the project end.
Day-counting convention. This lesson starts the project at day 0: ES of the first activity = 0, EF = ES + duration, and the next activity starts on the same number. Some books start at day 1: EF = ES + duration − 1, and the successor starts on EF + 1. Both give the same critical path and float. Choose one convention and use it throughout; exam questions usually make the convention clear or only ask about path lengths and float.
Day-0 convention: EF = ES + duration · LS = LF − duration.
The forward pass, step by step
The forward pass finds the early dates. Work from left to right.
| Activity | Rule applied | ES → EF |
|---|
| A | No predecessor: ES = 0 | 0 → 0 + 3 = 3 |
| E | No predecessor: ES = 0 | 0 → 0 + 6 = 6 |
| B | After A: ES = EF of A | 3 → 3 + 5 = 8 |
| C | After A: ES = EF of A | 3 → 3 + 2 = 5 |
| D | Merge: ES = largest EF of B, C, E = max(8, 5, 6) | 8 → 8 + 4 = 12 |
The project's earliest finish is day 12. Notice the merge rule at D: D cannot start until all its predecessors are finished, so it must wait for the latest one (B, at day 8).
Forward pass: EF = ES + duration. At a merge, take the largest EF.
The backward pass, step by step
The backward pass finds the late dates. Start at the end with LF = the project finish (12), and work from right to left.
| Activity | Rule applied | LF → LS |
|---|
| D | Last activity: LF = 12 | 12 → 12 − 4 = 8 |
| B | Before D: LF = LS of D | 8 → 8 − 5 = 3 |
| C | Before D: LF = LS of D | 8 → 8 − 2 = 6 |
| E | Before D: LF = LS of D | 8 → 8 − 6 = 2 |
| A | Burst: LF = smallest LS of B, C = min(3, 6) | 3 → 3 − 3 = 0 |
The burst rule at A is the mirror of the merge rule: A must finish early enough for every successor to start on time, so it must meet the earliest of their late starts (B, at day 3).
Backward pass: LS = LF − duration. At a burst, take the smallest LS.
Total float and free float
Total float belongs to a path, not to one activity. If two non-critical activities in a row share 4 days of float, and the first uses all 4, the second has none left. This is why free float matters: using free float never affects anyone else, while using total float may take slack away from later activities.
In our network the two values happen to be equal for C and E because each feeds directly into D. In longer chains they often differ.
Total float
Total float = LS − ES = LF − EF
How long an activity can be delayed without delaying the project end date. C: 6 − 3 = 3 days. E: 2 − 0 = 2 days.
Free float
Free float = ES of earliest successor − EF
How long an activity can be delayed without delaying any successor's early start. C: 8 − 5 = 3 days. E: 8 − 6 = 2 days.
Total float protects the project end; free float protects the next activity. Free float is always ≤ total float.
Identifying the critical path
When the project end date equals the calculated early finish, the critical path is the path where every activity has zero total float: here A → B → D. You can confirm it by adding path lengths: 12, 10 and 9 days. The longest path is critical.
A network can have more than one critical path. That is a riskier schedule, because a delay on any of them delays the project. Paths with only a little float, like E → D with 2 days, are near-critical; experienced schedulers watch them closely, because a small slip turns them critical.
Negative float
Sometimes the project has an imposed finish date that is earlier than the calculated early finish. If the client insists on move-in by day 10, the backward pass starts at LF = 10 instead of 12. Every activity on the critical path then has a total float of −2 days.
Negative float means the schedule, as planned, cannot meet the required date. It is a warning, not a mistake in the calculation. The project manager must respond: compress the schedule (crashing or fast tracking, next lesson), change the logic, reduce scope, or negotiate the date, through change control where the baseline is affected.
When activities slip: the critical path can change
If a non-critical activity is delayed by less than or equal to its total float, the end date does not move, but its float is used up. If it is delayed by more than its float, the end date moves by the difference, and its path may become the new critical path.
Example: C has 3 days of float. If C starts 4 days late, path A → C → D becomes 9 + 4 = 13 days, longer than A → B → D (12). The project finishes on day 13, and A → C → D is now critical.
This is why the critical path is recalculated whenever actual progress is recorded. It is a living result, not a fixed property of the plan.
Assumptions and limits of the critical path method
Unlimited resources. CPM assumes every activity can start as soon as its logic allows. If B and C need the same electrician, they cannot run in parallel, and the real critical path is longer. This is handled by resource leveling and the critical chain method (lesson 4 of this chapter).
Fixed durations. CPM uses one duration per activity. Real durations vary. When several paths merge, the chance that all of them finish on time is lower than for any single path (merge bias). That is why PERT estimates and Monte Carlo simulation are used for important dates.
Correct logic. The result is only as good as the dependencies. Missing links make the schedule look shorter than it really is. Good schedulers check that every activity except the first has a predecessor and every activity except the last has a successor.
Critical path in agile and hybrid projects
Pure agile teams rarely build activity networks for software, because the work inside a sprint is planned by the Developers and changes often. Agile teams manage dependencies through backlog ordering, cross-team planning and dependency boards.
In hybrid projects, CPM is still used for the parts with hard logic: construction, equipment delivery, installation and regulatory inspections. The PM integrates those milestones with the agile release plan, so that, for example, a software release is not planned before the hardware it depends on is installed.
Glossary
Key terms from this lesson, in simple words:
| Term | Meaning |
|---|
| Critical path | The longest path through the network; it sets the shortest project duration. |
| Activity-on-node (AON) | Network diagram where boxes are activities and arrows are dependencies. |
| Forward pass | Left-to-right calculation of early start and early finish. |
| Backward pass | Right-to-left calculation of late finish and late start. |
| Merge / burst | Activity with several predecessors / several successors. |
| Total float | Delay possible without moving the project end date. |
| Free float | Delay possible without moving any successor's early start. |
| Negative float | The plan cannot meet the required date by that many days. |
| Near-critical path | A path with very little float. |
| Merge bias | Lower chance of finishing on time where several paths join. |
Sources and further reading
Project Management Institute (PMI). PMP Examination Content Outline, July 2026.
PMI. Practice Standard for Scheduling, Third Edition.
PMI. A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Eighth Edition.
Kelley, J. E. and Walker, M. R. (1959). “Critical-Path Planning and Scheduling.” Proceedings of the Eastern Joint Computer Conference. The original CPM paper.
Kerzner, H. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Chapters on network scheduling.