Home › PMP lessons › Schedule

PMP lesson · Schedule · Schedule · lesson 2 of 4 · about 30 minutes

Critical path and float: forward pass, backward pass and what they mean

Predictive · also used for hardware in hybrid projectsFree full lesson
Goal: After this lesson you can build a forward and backward pass on a network diagram, calculate total and free float, identify the critical path (including when it changes), and explain what a delay does to the end date and what the method cannot tell you.
Open the full lesson →Free lesson. In the app you also get the quick check and your progress is saved.

1The situation

“Can we move in on day 12?”

You are managing the fit-out of a new office floor for an insurance company. The work has five activities: A demolition of the old interior (3 days), B electrical rough-in (5 days, after A), C IT cabling (2 days, after A), E furniture order and delivery (6 days, can start immediately), and D final inspection and move-in preparation (4 days, after B, C and E are all done).

The client's facilities manager asks two questions: “When is the earliest we can move in?” and “The cabling contractor says he may start late. Does that matter?”

Adding up all the durations (3 + 5 + 2 + 6 + 4 = 20 days) gives the wrong answer, because some work happens in parallel. You need to know which chain of activities controls the end date, and how much slack every other activity has.

That is what the critical path method (CPM) does. In this lesson you will calculate it by hand, step by step, and learn what it can and cannot tell you.

2Why the critical path matters

Every project has activities that can be delayed without hurting the end date, and activities that cannot. The critical path is the longest chain of dependent activities from start to finish. Its length is the shortest possible project duration.

Knowing it tells the project manager where to focus. A one-day slip on the critical path delays the whole project by one day. A one-day slip elsewhere may cost nothing. Without this knowledge, managers spread their attention evenly, or worse, put pressure on the wrong activities.

The method was developed in the late 1950s (DuPont and Remington Rand created CPM; the US Navy created PERT for the Polaris program at almost the same time). It remains the basis of every scheduling tool, from Microsoft Project to Primavera.

Critical path = the longest path through the network = the shortest time in which the project can be finished.

Reading a network diagram

A schedule network shows activities and the logic between them. In the activity-on-node (AON) format used by the PMP exam, each box (node) is an activity and each arrow is a dependency, usually finish-to-start: the next activity starts when the previous one finishes.

A path is any route from the start of the network to its end. Our office fit-out has three paths: A → B → D, A → C → D and E → D.

Two kinds of junction need special attention. A merge point is where several arrows come into one activity (D has three predecessors). A burst point is where one activity has several successors (A has two). These are exactly the places where the calculations need care.

The four dates of every activity

Early dates come from the forward pass (left to right). Late dates come from the backward pass (right to left). The difference between them is float.

ES
Early start
The earliest the activity can start, given its predecessors.
EF
Early finish
The earliest it can finish: ES + duration.
LS
Late start
The latest it can start without delaying the project end.
LF
Late finish
The latest it can finish without delaying the project end.

Day-counting convention. This lesson starts the project at day 0: ES of the first activity = 0, EF = ES + duration, and the next activity starts on the same number. Some books start at day 1: EF = ES + duration − 1, and the successor starts on EF + 1. Both give the same critical path and float. Choose one convention and use it throughout; exam questions usually make the convention clear or only ask about path lengths and float.

Day-0 convention: EF = ES + duration · LS = LF − duration.

The forward pass, step by step

The forward pass finds the early dates. Work from left to right.

ActivityRule appliedES → EF
ANo predecessor: ES = 00 → 0 + 3 = 3
ENo predecessor: ES = 00 → 0 + 6 = 6
BAfter A: ES = EF of A3 → 3 + 5 = 8
CAfter A: ES = EF of A3 → 3 + 2 = 5
DMerge: ES = largest EF of B, C, E = max(8, 5, 6)8 → 8 + 4 = 12

The project's earliest finish is day 12. Notice the merge rule at D: D cannot start until all its predecessors are finished, so it must wait for the latest one (B, at day 8).

Forward pass: EF = ES + duration. At a merge, take the largest EF.

The backward pass, step by step

The backward pass finds the late dates. Start at the end with LF = the project finish (12), and work from right to left.

ActivityRule appliedLF → LS
DLast activity: LF = 1212 → 12 − 4 = 8
BBefore D: LF = LS of D8 → 8 − 5 = 3
CBefore D: LF = LS of D8 → 8 − 2 = 6
EBefore D: LF = LS of D8 → 8 − 6 = 2
ABurst: LF = smallest LS of B, C = min(3, 6)3 → 3 − 3 = 0

The burst rule at A is the mirror of the merge rule: A must finish early enough for every successor to start on time, so it must meet the earliest of their late starts (B, at day 3).

Backward pass: LS = LF − duration. At a burst, take the smallest LS.

Total float and free float

Total float belongs to a path, not to one activity. If two non-critical activities in a row share 4 days of float, and the first uses all 4, the second has none left. This is why free float matters: using free float never affects anyone else, while using total float may take slack away from later activities.

In our network the two values happen to be equal for C and E because each feeds directly into D. In longer chains they often differ.

Total float
Total float = LS − ES = LF − EF
How long an activity can be delayed without delaying the project end date. C: 6 − 3 = 3 days. E: 2 − 0 = 2 days.
Free float
Free float = ES of earliest successor − EF
How long an activity can be delayed without delaying any successor's early start. C: 8 − 5 = 3 days. E: 8 − 6 = 2 days.
Total float protects the project end; free float protects the next activity. Free float is always ≤ total float.

Identifying the critical path

When the project end date equals the calculated early finish, the critical path is the path where every activity has zero total float: here A → B → D. You can confirm it by adding path lengths: 12, 10 and 9 days. The longest path is critical.

A network can have more than one critical path. That is a riskier schedule, because a delay on any of them delays the project. Paths with only a little float, like E → D with 2 days, are near-critical; experienced schedulers watch them closely, because a small slip turns them critical.

Negative float

Sometimes the project has an imposed finish date that is earlier than the calculated early finish. If the client insists on move-in by day 10, the backward pass starts at LF = 10 instead of 12. Every activity on the critical path then has a total float of −2 days.

Negative float means the schedule, as planned, cannot meet the required date. It is a warning, not a mistake in the calculation. The project manager must respond: compress the schedule (crashing or fast tracking, next lesson), change the logic, reduce scope, or negotiate the date, through change control where the baseline is affected.

When activities slip: the critical path can change

If a non-critical activity is delayed by less than or equal to its total float, the end date does not move, but its float is used up. If it is delayed by more than its float, the end date moves by the difference, and its path may become the new critical path.

Example: C has 3 days of float. If C starts 4 days late, path A → C → D becomes 9 + 4 = 13 days, longer than A → B → D (12). The project finishes on day 13, and A → C → D is now critical.

This is why the critical path is recalculated whenever actual progress is recorded. It is a living result, not a fixed property of the plan.

Assumptions and limits of the critical path method

Unlimited resources. CPM assumes every activity can start as soon as its logic allows. If B and C need the same electrician, they cannot run in parallel, and the real critical path is longer. This is handled by resource leveling and the critical chain method (lesson 4 of this chapter).

Fixed durations. CPM uses one duration per activity. Real durations vary. When several paths merge, the chance that all of them finish on time is lower than for any single path (merge bias). That is why PERT estimates and Monte Carlo simulation are used for important dates.

Correct logic. The result is only as good as the dependencies. Missing links make the schedule look shorter than it really is. Good schedulers check that every activity except the first has a predecessor and every activity except the last has a successor.

Critical path in agile and hybrid projects

Pure agile teams rarely build activity networks for software, because the work inside a sprint is planned by the Developers and changes often. Agile teams manage dependencies through backlog ordering, cross-team planning and dependency boards.

In hybrid projects, CPM is still used for the parts with hard logic: construction, equipment delivery, installation and regulatory inspections. The PM integrates those milestones with the agile release plan, so that, for example, a software release is not planned before the hardware it depends on is installed.

Glossary

Key terms from this lesson, in simple words:

TermMeaning
Critical pathThe longest path through the network; it sets the shortest project duration.
Activity-on-node (AON)Network diagram where boxes are activities and arrows are dependencies.
Forward passLeft-to-right calculation of early start and early finish.
Backward passRight-to-left calculation of late finish and late start.
Merge / burstActivity with several predecessors / several successors.
Total floatDelay possible without moving the project end date.
Free floatDelay possible without moving any successor's early start.
Negative floatThe plan cannot meet the required date by that many days.
Near-critical pathA path with very little float.
Merge biasLower chance of finishing on time where several paths join.

Sources and further reading

Project Management Institute (PMI). PMP Examination Content Outline, July 2026.

PMI. Practice Standard for Scheduling, Third Edition.

PMI. A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Eighth Edition.

Kelley, J. E. and Walker, M. R. (1959). “Critical-Path Planning and Scheduling.” Proceedings of the Eastern Joint Computer Conference. The original CPM paper.

Kerzner, H. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Chapters on network scheduling.

3See it in one picture: the network with all four dates

Network diagram with early and late dates03d3A Demolition0TF 0335d8B Electrical3TF 0832d5C IT cabling6TF 3806d6E Furniture2TF 2884d12D Inspection8TF 012
How to read a node: top row = ES · duration · EF; bottom row = LS · total float · LF. Red = critical path (zero float).
Forward pass gives the top row; backward pass gives the bottom row. Activities with zero total float (red) form the critical path A → B → D: 12 days.

Check by path length

PathLengthFloat
A → B → D3 + 5 + 4 = 12 days0 (critical)
E → D6 + 4 = 10 days2 days
A → C → D3 + 2 + 4 = 9 days3 days

4Worked example: the cabling contractor starts 4 days late

Given: Same network as the Picture section. The cabling contractor says C cannot start until day 7 instead of day 3 (a 4-day delay). Everything else stays the same.
1. Find C's floatTotal float of C = LS − ES = 6 − 3 = 3 daysC can absorb up to 3 days.
2. Compare delay and floatDelay 4 days > float 3 daysThe end date will move.
3. New forward pass for CES = 7, EF = 7 + 2 = 9C now finishes on day 9.
4. Merge at DES of D = max(B 8, C 9, E 6) = 9 → EF = 13D must wait for C.
5. New critical pathA → C → D now ends on day 13; A → B → D has 1 day of floatThe critical path has changed.
6. Sanity checkProject delay = delay − float = 4 − 3 = 1 dayMatches: 13 − 12 = 1 day.
Tell the facilities manager: the late cabling start delays move-in by 1 day (day 13), and cabling is now on the critical path. Options: ask the contractor to add a second crew to finish C in 1 day, or start cabling in the areas already demolished; assess cost and risk, then decide with the sponsor if the end date matters.

5Wrong vs right: the common traps

✘ Wrong thinking
“Add up all the durations to get the project length.”
✔ Right thinking
Parallel work overlaps. The project length is the longest path, not the sum (12 days, not 20).
✘ Wrong thinking
“At a merge point, use the smallest early finish.”
✔ Right thinking
An activity waits for all its predecessors: use the largest EF. In the backward pass at a burst, use the smallest LS.
✘ Wrong thinking
“C has 3 days of float, so a 4-day delay costs 4 days.”
✔ Right thinking
Only the delay beyond float moves the end date: 4 − 3 = 1 day.
✘ Wrong thinking
“The critical path is fixed once the plan is approved.”
✔ Right thinking
It changes when actual progress changes the dates. Recalculate after every update.
✘ Wrong thinking
“Every activity in a chain has its own float that it can use.”
✔ Right thinking
Total float is shared along the path. Free float belongs to the activity alone.
✘ Wrong thinking
“Negative float means the calculation is wrong.”
✔ Right thinking
It means the plan cannot meet the imposed date. The PM must compress, change logic, reduce scope or renegotiate.
✘ Wrong thinking
“The critical path contains the most important activities.”
✔ Right thinking
It contains the activities with no slack. Important but non-critical work (e.g. a safety review with float) still needs control.

6How it looks on the exam

Exam-style question 1. A network has three paths: Start–P–Q–End (12 days), Start–R–S–End (15 days) and Start–T–End (14 days). Activity T is delayed by 2 days. What is the effect on the project?
A. The project is delayed by 2 days, because T is on a path
B. The project is not delayed, because T is not on the critical path
C. The project is delayed by 1 day, and T's path becomes critical
D. The project is delayed by 3 days, because float is lost on two paths
Show the answer and the decode
Answer: C.
What it means
Three paths; the critical one is 15 days. T is on the 14-day path, so it has 1 day of float.
What is the question really asking?
What a 2-day delay to T does to the end date.
Key words / trigger
“delayed by 2 days”
PMP logic
T's path becomes 14 + 2 = 16 days, longer than 15. The project moves by 2 − 1 = 1 day, and Start–T–End becomes the new critical path. If T had been on the 12-day path, a 2-day delay would cost nothing.
Why the wrong answer looks attractive
A: ignores T's 1 day of float. B: true only if the delay were 1 day or less. D: float is not added across paths; only the longest path sets the end date.
Exam-style question 2. During the forward pass, activity M has three predecessors with early finish dates of day 10, day 14 and day 12. Using the day-0 convention, what is the early start of M?
A. Day 14
B. Day 10
C. Day 12
D. Day 36
Show the answer and the decode
Answer: A.
What it means
A merge point in the forward pass.
What is the question really asking?
Which predecessor date controls the early start.
Key words / trigger
“three predecessors · early finish”
PMP logic
M cannot start until all three predecessors are finished, so its ES is the largest EF: day 14. With the day-1 convention it would be day 15.
Why the wrong answer looks attractive
B: the smallest EF is the backward-pass burst rule, applied in the wrong direction. C: there is no averaging in CPM. D: early finishes are dates, not durations; they are never added.
Exam-style question 3. A project's calculated early finish is day 60, but the contract requires completion by day 54. The scheduling tool now shows a total float of −6 days on several activities. What should the project manager do first?
A. Report that the scheduling tool has calculated the float wrongly
B. Ask the team to work faster on all activities that show negative float
C. Change the contract completion date in the schedule to day 60
D. Analyze compression options for the critical path and present them
Show the answer and the decode
Answer: D.
What it means
The plan cannot meet the contract date: negative float of 6 days.
What is the question really asking?
The first appropriate action.
Key words / trigger
“total float of −6 days”
PMP logic
Negative float is a real warning. Analyze options (crashing, fast tracking, logic changes, scope) on the critical path, with cost and risk, then present them to the sponsor. If no option works, a change request to the contract date may follow, through the proper process.
Why the wrong answer looks attractive
A: the calculation is correct; the plan is the problem. B: vague pressure on every activity is not a plan and wastes effort on non-critical work. C: changing a contractual date without agreement is not within the PM's authority.
Exam-style question 4. Activity K has an early finish of day 9 and a total float of 4 days. Its only successor, activity L, has an early start of day 11. How much can K be delayed without delaying L?
A. 4 days
B. 2 days
C. 0 days
D. 6 days
Show the answer and the decode
Answer: B.
What it means
K has total float 4, and there is a gap of 2 days before its successor starts.
What is the question really asking?
Free float of K.
Key words / trigger
“without delaying L”
PMP logic
Free float = ES of successor − EF = 11 − 9 = 2 days. K could use up to 4 days (total float) without delaying the project, but after 2 days it begins to push L.
Why the wrong answer looks attractive
A: that is total float, which protects the project end, not the successor. C: K is not critical, so it has slack. D: adds the two numbers; float values are never added.
Exam-style question 5. The facilities manager offers to pay overtime so that a non-critical activity with 5 days of total float finishes 3 days earlier. The sponsor wants the project end date earlier. What should the project manager explain?
A. The overtime will move the end date 3 days earlier, as requested
B. The overtime should be used, because finishing any activity early helps
C. The end date will not move, because the activity is not on the critical path
D. The end date will move 2 days earlier, which is the remaining float
Show the answer and the decode
Answer: C.
What it means
Money is offered to speed up an activity that already has slack.
What is the question really asking?
The effect on the end date.
Key words / trigger
“non-critical activity with 5 days of total float”
PMP logic
Shortening a non-critical activity only adds to its float; the longest path, and therefore the end date, is unchanged. Money should go to critical-path activities. Overtime there could make sense if another path were only slightly shorter.
Why the wrong answer looks attractive
A: assumes every activity drives the end date. B: spending on non-critical work wastes money. D: an invented calculation; float is not converted into earlier finish.

7Remember this

Your memory card

  • Critical path = longest path = shortest project duration; zero total float when the end date equals the early finish
  • Forward pass: EF = ES + duration; at a merge take the largest EF
  • Backward pass: LS = LF − duration; at a burst take the smallest LS
  • Total float = LS − ES (protects the end date); free float = successor's ES − EF (protects the next activity)
  • Delay beyond float moves the end date by (delay − float); the critical path can change
  • Negative float = the plan cannot meet the imposed date → compress, change logic, reduce scope or renegotiate
  • CPM assumes unlimited resources and fixed durations → resource leveling, critical chain, PERT and Monte Carlo fill the gaps

📘 Quick reference: Study guide: Critical path and float, with a worked example · Practice more PMP questions

Do the quick check in the app →Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.