PMP lesson · Stakeholders & Communication · Stakeholders and communication · lesson 1 of 4 · about 7 minutes
Identifying and analysing stakeholders
All approachesFree preview
Goal: After this lesson you can identify stakeholders early, classify them on a power/interest grid, and use an engagement assessment matrix to plan where to focus.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
1The situation
The person nobody invited
The robot cell is half installed when the operators' union representative hears that “automation means layoffs”. Nobody had invited the union to any meeting. Now the representative threatens to oppose the start-up.
Management says no jobs will be lost; operators will be retrained. But nobody told the people affected, and the rumour spread faster than the facts.
Stakeholders you forget do not disappear. They appear later, when they are hardest to manage.
2Who is a stakeholder?
Anyone who can affect the project, or who is affected by it (or thinks they are). Identify them early and keep identifying them: new stakeholders appear when organisations change.
Identify
Early and often
Brainstorm, check the charter, contracts, org charts, lessons learned.
Analyse
Power and interest
How much influence? How much do they care? What do they expect?
Register
Stakeholder register
Name, role, expectations, influence, engagement level, communication needs.
Exam-style question 1. Midway through the project, the customer reorganises its engineering and maintenance departments under a newly hired director who has not yet been involved. What should the project manager do?
A. Continue working with the previous stakeholders until the structure settles
B. Update the stakeholder register, analyse the new director's interests and influence, and engage the director early
C. Wait for the director to make contact
D. Ask the sponsor to brief the director instead
Show the answer and the decode
Answer: B.
What it means
A new, influential person now affects the project.
What is the question really asking?
The right response.
Key words / trigger
“newly hired director … not yet been involved”
PMP logic
Stakeholder identification is continuous; new key stakeholders are analysed and engaged early.
Why the wrong answer looks attractive
The sponsor may help, but engagement remains the PM's responsibility.
5Remember this
Your memory card
Stakeholders = anyone who affects or is affected; identify early and continuously