Home › Study guides › PMP question words

PMP Question Words Explained: FIRST, NEXT, BEST, EXCEPT, SHOULD HAVE

PMP questions use a special kind of English. Often one small word decides the answer. Learn to spot these words, and you won’t need to translate every sentence.

The one habit that helps most

Read the last sentence of the question first. It tells you what kind of answer is wanted. Then read the story and look for the words below.

1. Question words

WordWhat it meansHow to answer
FIRSTWhat should the PM do before anything else?Usually: assess, analyze, review the plan, or talk to the person. Usually not: escalate, replace someone, or change the baseline.
NEXTSomething has already happened. What is the next logical step?Read what was already done, and don't choose it again. Pick the step that comes right after it.
BESTSeveral answers could work. Choose the strongest one.Prefer the answer that is proactive, collaborative and follows the agreed process.
MOST LIKELYWhat is the most probable cause or result?Think about what normally happens, not what could happen in rare cases.
SHOULD HAVELook backward. What would have prevented this problem?The answer is usually a planning step that was skipped: a register, a plan, an analysis.
EXCEPTThree answers are correct. Choose the one that is NOT.Read every option, mark the true ones, and pick the one left over.
NOTThe question asks for the wrong or false item.Slow down. Capital NOT flips the question around.
PRIMARY / MAINWhat is the most important purpose or reason?Several options may be true; choose the central one.
ALREADYThis step is done.Don't pick an answer that repeats it; move to what comes after.

Example

“A team member tells you a key supplier will deliver two weeks late. What should the project manager do FIRST?” The word FIRST tells you to look for the step before any action: assess the impact on the schedule, not “escalate to the sponsor” or “find a new supplier.”

2. Small words that change the answer

Don’t translate every word. Notice these phrases.

When the question says…Think…Study guide
“identified risk”, “known risk”Think: planned response, contingency reserveRisk responses: escalate, avoid, transfer, mitigate, accept
“not previously identified”, “unforeseen”Think: workaround, management reserveContingency reserve vs management reserve
“external systems” + “boundary”Think: context diagram
“the customer did not request”Think: gold plating (don't do it)Scope planning: requirements, WBS, baseline
“before taking action”Think: assess or analyze firstIntegrated change control
“two other sellers are bidding”Think: procurement fairness, equal formal communication
“the charter will follow”Think: the project is not authorized yetProject charter
“limited capacity” + many defect categoriesThink: prioritize the biggest causes, Pareto chartQuality tools: Pareto, fishbone, control chart
“the risk has occurred”Think: implement the planned responseRisk responses: escalate, avoid, transfer, mitigate, accept
“may happen” vs “has happened”Think: risk vs issue
“work remaining”Think: burndown chart
“the customer keeps adding features”Think: burnup chart shows scope growth
“too much work in progress”Think: Kanban WIP limit, finish before starting
“how the team worked”Think: retrospectiveRetrospective
“what was delivered”Think: sprint review
“blocked”, “waiting for”Think: impediment, the servant leader removes it
“from another department”Think: negotiate with the functional manager
“fixed-price contract” + new requestThink: formal contract change
“the end date cannot change” + overloadThink: resource smoothingResource leveling vs resource smoothing
“on time and on budget, but…”Think: value and benefits are the real measure
“a new stakeholder appears”Think: add to the register and analyzeStakeholders: identify, engage, monitor
“phase gate”, “kill point”Think: is the project still justified?
“safety hazard”, “emergency”Think: act immediately, safety first
“mandatory” vs “preferred” orderThink: mandatory vs discretionary dependency
Practise with these words highlighted

In the PMCLEAR app, every question shows its question word and what it means. The full PMP English Decoder (with 20 key verbs) is free.

Open the free PMP English Decoder →