Home › Study guides › Earned value: CPI, SPI, EAC, ETC, VAC

Earned Value Formulas Explained Simply: CPI, SPI, EAC, ETC, VAC

Earned value compares planned work, completed work and actual cost to show schedule and cost performance.

In simple words

Earned Value answers one simple question: are we getting the work we planned, for the money we planned? It compares three numbers: Planned Value (the work we planned to finish by today), Earned Value (the work we really finished) and Actual Cost (what it really cost). An index below 1 is bad news: CPI below 1 means over budget, SPI below 1 means behind schedule.

What the PMP exam wants

PV (planned value) = budgeted cost of work planned to date. EV (earned value) = budgeted cost of work actually done. AC (actual cost) = what the done work really cost. SV = EV − PV; CV = EV − AC. SPI = EV ÷ PV; CPI = EV ÷ AC. Below 1 is bad: SPI < 1 = behind schedule, CPI < 1 = over budget. Above 1 is good.

Forecasts: which EAC to use depends on what the question says. Current performance will continue: EAC = BAC ÷ CPI. The problem was one-time and will not continue: EAC = AC + (BAC − EV). The original estimate is no longer valid: EAC = AC + a new bottom-up ETC. Both cost and schedule problems will continue: EAC = AC + (BAC − EV) ÷ (CPI × SPI). ETC = EAC − AC. VAC = BAC − EAC: positive VAC means you expect to finish under budget, negative means over budget (the “below 1” rule does not apply to VAC). TCPI = (BAC − EV) ÷ (BAC − AC): TCPI above 1 means the remaining work must be done more efficiently than the work so far.

Real example

PV = $100k, EV = $80k, AC = $90k. SPI = 80 ÷ 100 = 0.80 (behind). CPI = 80 ÷ 90 ≈ 0.89 (over budget). With BAC = $500k, EAC = 500 ÷ 0.89 ≈ $562k.

Try it with your own numbers: the free earned value calculator from DailyDebian takes your PV, EV and AC and works out SV, CV, SPI, CPI, EAC, ETC, VAC and TCPI, showing every formula.

The common trap

“SPI is time, CPI is money” is a good start, but SPI measures schedule in the value of work done, not in days. A project can be ahead of schedule (SPI > 1) and over budget (CPI < 1) at the same time.

Remember: EV comes first in every formula. For CPI and SPI, less than 1 = bad. For CV, SV and VAC, negative = bad.

🗝 Words to notice in the question

“CPI”, “SPI”, “EV, PV, AC” → below 1 is bad

Try 2 practice questions

Choose an answer, or open “Show the answer.”

Question 1 A project has CPI = 0.85 and SPI = 1.10. What does this mean?

Show the answer

Answer: C. CPI < 1 = spending more than planned for the work done. SPI > 1 = more work done than planned.

Question 2 PV = 200, EV = 160, AC = 180. What is the SPI?

Show the answer

Answer: A. SPI = EV ÷ PV = 160 ÷ 200 = 0.80, so behind schedule. (CPI = 160 ÷ 180 ≈ 0.89, over budget.)

Continue learning with PMCLEAR

The free demo has this chapter with the key words, the PMP rule and every wrong answer explained. No sign-up, no card.

Open the free chapter → Practice more PMP questions

Related study guides