Earned Value Formulas Explained Simply: CPI, SPI, EAC, ETC, VAC

Earned value compares planned work, completed work and actual cost to show schedule and cost performance.

In simple words

Earned Value answers one simple question: are we getting the work we planned, for the money we planned? It compares three numbers: Planned Value (the work we planned to finish by today), Earned Value (the work we really finished) and Actual Cost (what it really cost). An index below 1 is bad news: CPI below 1 means over budget, SPI below 1 means behind schedule.

What the PMP exam wants

PV (planned value) = budgeted cost of work planned to date. EV (earned value) = budgeted cost of work actually done. AC (actual cost) = what the done work really cost. SV = EV − PV; CV = EV − AC. SPI = EV ÷ PV; CPI = EV ÷ AC. Below 1 is bad: SPI < 1 = behind schedule, CPI < 1 = over budget. Above 1 is good.

Forecasts: EAC (estimate at completion) = BAC ÷ CPI if current performance continues. ETC (estimate to complete) = EAC − AC. VAC = BAC − EAC. For the exam, know what the numbers mean; deep calculation is rare.

Real example

PV = $100k, EV = $80k, AC = $90k. SPI = 80 ÷ 100 = 0.80 (behind). CPI = 80 ÷ 90 ≈ 0.89 (over budget). With BAC = $500k, EAC = 500 ÷ 0.89 ≈ $562k.

The common trap

SPI is time, CPI is money. A project can be ahead of schedule (SPI > 1) and over budget (CPI < 1) at the same time.

Remember: EV comes first in every formula. Less than 1 = bad.

🗝 Words to notice in the question

“CPI”, “SPI”, “EV, PV, AC” → below 1 is bad

Try 2 practice questions

Choose an answer, or open “Show the answer.”

Question 1 A project has CPI = 0.85 and SPI = 1.10. What does this mean?

Show the answer

Answer: C. CPI < 1 = spending more than planned for the work done. SPI > 1 = more work done than planned.

Question 2 PV = 200, EV = 160, AC = 180. What is the SPI?

Show the answer

Answer: A. SPI = EV ÷ PV = 160 ÷ 200 = 0.80, so behind schedule. (CPI = 160 ÷ 180 ≈ 0.89, over budget.)

Study the full chapter for free

The free demo has this chapter with the key words, the PMP rule and every wrong answer explained. No sign-up, no card.