PMP lesson · Cost & EVM · Cost: estimating, budget and earned value · lesson 1 of 5 · about 30 minutes
Estimating techniques: analogous, parametric, three-point and bottom-up
Predictive · agile teams use relative estimation (story points)Free preview
Goal: After this lesson you can choose the right estimating technique for the stage and information available, calculate PERT and triangular estimates with their standard deviation and ranges, combine uncertainty along a path, and explain the biases and accuracy ranges behind every estimate.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
1The situation
“Just give me a number”
A regional bank is moving its call center to a new 8,000-square-foot office. The facilities director asks you for an estimate of the electrical and data cabling work. “Just give me a number for the board meeting on Friday.”
You have very little detail yet: no drawings, only a floor area. But you remember that a similar office last year cost about $90,000, and your electrical contractor quotes a typical rate of $12 per square foot. Later, when drawings exist, you will be able to estimate every work package separately.
Each of these is a different estimating technique, with a different accuracy and cost. And every estimate hides uncertainty: the cabling might take 8 days if everything goes well, or 22 days if the old ceiling hides problems.
This lesson explains the four main techniques, how to put a number on uncertainty with three-point estimates, how accurate an estimate can be at each stage, and why people consistently estimate too low.
2What an estimate is, and what it is not
An estimate is a quantified assessment of the likely amount of something (cost, duration, effort or resources), based on the information available at the time. It is a forecast, not a promise and not a target.
Three quantities are often confused. Effort is the work needed, in person-hours or person-days. Duration is the number of working periods the activity takes, which depends on how many people work on it. Elapsed time is calendar time, including weekends and holidays. Forty hours of effort may be one week of duration for one person, or half a week for two.
Every estimate should come with its basis of estimate: the assumptions, the method, the source data and the expected range. “$96,000, parametric, $12/sq ft from the contractor's last three jobs, ±25%” is far more useful than “$96,000”.
An estimate = a number + its range + its assumptions. A single number without a range hides the uncertainty.
3See it in one picture: an estimate is a range
PERT gives 13 days, but the real outcome will be somewhere in a range. Dark band ≈ 68% of outcomes (10.7–15.3 days); light band ≈ 95% (8.3–17.7 days). The pessimistic tail is longer than the optimistic one.
4How it looks on the exam
Exam-style question 1. The sponsor needs a cost estimate for a new warehouse project by tomorrow for a portfolio review. Only the floor area and the cost of a similar warehouse built two years ago are known. Which technique should the project manager use?
A. Bottom-up estimating based on the work breakdown structure
B. Analogous estimating, adjusted for known differences
C. Three-point estimating for every activity in the schedule
D. Vendor bid analysis after issuing a request for proposal
Show the answer and the decode
Answer: B.
What it means
Very early, little detail, very little time, a similar past project exists.
What is the question really asking?
The appropriate technique.
Key words / trigger
“by tomorrow · a similar warehouse”
PMP logic
Analogous estimating is fast and uses a similar past project, adjusted for differences such as size and inflation. With a reliable cost per square meter, parametric would also fit. Bottom-up would be right later, once a WBS exists.
Why the wrong answer looks attractive
A: there is no WBS yet, and no time. C: there is no activity list to estimate. D: an RFP process takes weeks and is part of procurement, not a first estimate.
5Remember this
Your memory card
Estimate = number + range + assumptions (basis of estimate); effort ≠ duration
Analogous: similar past project, fast, least accurate · Parametric: rate × quantity · Bottom-up: sum of work packages, most accurate
Triangular (O + M + P) ÷ 3 · PERT (O + 4M + P) ÷ 6 · σ ≈ (P − O) ÷ 6
±1σ ≈ 68%, ±2σ ≈ 95%: plan to the confidence you need, with contingency
Along a path: means add, variances add, σ does not
ROM −25% to +75% → definitive −5% to +10% as detail grows (cone of uncertainty)
Biases: planning fallacy, anchoring; padding is eaten by Parkinson's law and student syndrome
Agile: relative estimates (story points, planning poker); duration comes from velocity
The full lesson in the PMCLEAR app also has:
the rest of the lesson (Analogous estimating, Parametric estimating, Bottom-up estimating, Three-point estimating, What the standard deviation tells you, Uncertainty along a path, Accuracy at each stage: the cone of uncertainty, Why estimates are usually too low, Estimating in agile teams, Glossary, Sources and further reading)
Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.