PMP lesson · Schedule · Schedule · lesson 4 of 4 · about 6 minutes
Resource levelling vs resource smoothing
Predictive · hybridFree preview
Goal: After this lesson you can explain the difference between levelling and smoothing, and predict what each does to the end date and the critical path.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
1The situation
Four welders on a two-welder team
The robot cell schedule looks fine on paper: 10 days. But on days 3 and 4 it needs four welders, and the company has only two.
You have two choices: move work so that no day needs more than two welders, even if the project gets longer, or only move work inside its float so that the end date stays the same, accepting that some peaks may remain.
These are resource levelling and resource smoothing.
2Two ways to fix resource problems
Both start from a resource histogram: a bar chart showing how many people are needed each day.
Levelling
Respect the limit
Moves work until no day exceeds the available resources. The end date can move and the critical path can change.
Smoothing
Stay within float
Moves work only within float. The end date does not move; some over-allocation may remain.
Exam shortcut: “end date cannot change” → smoothing. “limited resources, date may move” → levelling.
3See it in one picture
Before: days 3–5 need more welders than available (red). After levelling: never more than 2, but the work takes longer.
4How it looks on the exam
Exam-style question 1. The customer will not accept any change to the go-live date. The resource histogram shows that two electricians are over-allocated during week 6, and some of their activities have float. Which technique should the project manager use?
A. Resource levelling
B. Resource smoothing
C. Fast tracking
D. Crashing
Show the answer and the decode
Answer: B.
What it means
Too much work for the electricians in one week, but the date cannot move.
What is the question really asking?
The right technique.
Key words / trigger
“will not accept any change to the go-live date … have float”
PMP logic
Smoothing moves work within float without changing the end date.
Why the wrong answer looks attractive
Levelling also fixes over-allocation, but it may delay the project.
5Remember this
Your memory card
Levelling = respect resource limits; end date and critical path can change
Smoothing = even out usage within float; end date does not change
Start from the resource histogram
After levelling: recheck the critical path; baseline changes go through change control