PMP lesson · Schedule · Schedule · lesson 3 of 4 · about 30 minutes
Schedule compression: crashing, fast tracking and the time–cost trade-off
Predictive · also used for hardware in hybrid projectsFree preview
Goal: After this lesson you can calculate cost slopes and choose which activities to crash, explain when fast tracking is the better option, find the point where compression stops paying for itself, and recognize the risks and limits of both techniques.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.
1The situation
“Open two weeks earlier, please”
You are managing the fit-out of a new sporting-goods store in a shopping mall. The schedule says 15 working days to opening. Then the mall owner calls: a large neighboring store opens on day 12, and the client wants to open the same day to catch the crowds.
The client's operations director asks: “How much would it cost to finish three days earlier? And is there a way to do it without spending more?”
There are two classic answers. Crashing adds resources (overtime, extra crews, faster delivery) to shorten critical activities, and it costs money. Fast tracking overlaps activities that were planned in sequence, and it costs risk.
This lesson shows how to choose the cheapest days to buy, why the critical path can change while you compress, where compression stops paying off, and how to explain the trade-offs to a sponsor.
2What schedule compression is
Schedule compression means shortening the schedule without reducing the project scope. It is used when a new deadline is imposed, when the project has fallen behind, or when finishing early creates value (earlier revenue, avoided penalties, a market opportunity).
There are two main techniques: crashing and fast tracking. Both work only on the critical path, because only critical activities control the end date. Shortening an activity with float simply gives it more float.
If neither technique is acceptable, the remaining options are to reduce scope (with the sponsor's agreement), change the approach or technology, accept the later date, or negotiate the deadline. These decisions usually go through change control, because they affect the baseline.
Compression = same scope, shorter time. Work only on the critical path, and re-check the critical path after every step.
3See it in one picture: which days are worth buying?
Each bar is the extra cost of saving one more day. Below the green line, the day pays for itself through overhead saved. The third day costs $500 more than it saves, so it is worth buying only if opening on day 12 is worth at least that much more.
4How it looks on the exam
Exam-style question 1. A project is two weeks behind schedule. The sponsor says no additional funds are available, but the deadline cannot move. Several critical activities follow each other only because the team prefers that order. What should the project manager do?
A. Crash the critical activities using paid overtime for the team
B. Fast-track the critical activities with discretionary sequencing
C. Reduce the project scope without consulting the sponsor
D. Crash the non-critical activities that have the lowest cost
Show the answer and the decode
Answer: B.
What it means
Behind schedule, no extra money, fixed deadline, and some logic is only a preference.
What is the question really asking?
The best compression technique.
Key words / trigger
“no additional funds · prefers that order”
PMP logic
Fast tracking overlaps discretionary activities without extra money, at the cost of added risk, which must be assessed and recorded. If money were available and risk had to stay low, crashing would be the better answer.
Why the wrong answer looks attractive
A: crashing needs money the sponsor has refused. C: scope changes need the sponsor's approval through change control. D: non-critical activities do not control the end date.
5Remember this
Your memory card
Compression = same scope, shorter time; only the critical path matters
Crashing adds resources and money; cost slope = (crash cost − normal cost) ÷ (normal − crash duration)
Crash the cheapest critical activity, one day at a time, and re-check all paths
Two critical paths → shorten both: a shared activity or one on each path
Stop when the next day costs more than it is worth (indirect cost saved, bonus, revenue)
Fast tracking overlaps discretionary logic; little cost, more risk and rework
No budget → fast track · low risk tolerance or hard logic → crash
Diminishing returns and Brooks's law: more people is not always faster
the rest of the lesson (Crashing: buying time with money, Crashing step by step, The time–cost trade-off, Fast tracking: buying time with risk, Crashing or fast tracking: how to choose, Why adding people does not always help, Other ways to shorten a schedule, Risks created by compression, Compression in agile and hybrid projects, How PMI tests compression, Glossary, Sources and further reading)
Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.