PMP lesson · Cost & EVM · Cost: estimating, budget and earned value · lesson 3 of 5 · about 30 minutes

Earned value basics: PV, EV, AC, variances and performance indexes

Predictive · also used in hybrid reportingFree preview
Goal: After this lesson you can explain why earned value is needed, measure EV with an appropriate method, calculate CV, SV, CPI and SPI and their percentages, interpret them correctly in one sentence, and explain the main limits of the method.
Open the full lesson →This page is a preview. The full lesson, with examples, traps and exam questions, is in the PMCLEAR app.

1The situation

“We have spent half the budget. Are we halfway?”

You are managing the installation of a new nurse-call and patient-monitoring system in a 200-bed hospital. The budget is $400,000 over 10 months. At the end of month 5, the finance report says $220,000 has been spent.

The hospital's chief operating officer asks: “We have spent a little more than half the money in half the time. That sounds about right. Are we on track?”

You cannot answer from spending alone. Spending tells you what you paid, not what you got. Maybe the team has done more work than planned; maybe much less. To know, you must compare three numbers: what you planned to do, what you actually did, and what it cost.

That is earned value management (EVM). This lesson explains its three basic measures, how to measure the work actually done, the four main indicators, and how to read them without the common mistakes.

2Why spending alone tells you nothing

A project can have spent exactly the planned amount and still be in trouble, if the work done is far behind. It can also be over budget by month 5 simply because it is ahead of schedule. Spending and schedule must be judged together, against the work actually completed.

Earned value management integrates scope, schedule and cost into one set of measures. It was developed for US defense programs in the 1960s and is now a standard (ANSI/EIA-748 in the United States, and PMI's Standard for Earned Value Management). It answers two questions objectively: are we ahead or behind schedule? and are we over or under budget?

Older textbooks use different names for the same three measures: BCWS (budgeted cost of work scheduled) for PV, BCWP (budgeted cost of work performed) for EV, and ACWP (actual cost of work performed) for AC. The long names are useful because they say exactly what each measure is. If you meet them in other sources, they are not new concepts.

EVM is built on the time-phased cost baseline from the previous lesson. Without a baseline that links budget to scope and time, there is nothing to compare against.

3See it in one picture: the three curves

PV, EV and AC at month 50k100k200k300k400k0246810Status: month 5CV −60kSV −40kPV planEV earnedAC actualMonth
At month 5 the plan (PV, blue) says $200,000 of work should be done. Only $160,000 has been earned (EV, green), and it cost $220,000 (AC, red). EV is below PV: behind schedule. AC is above EV: over budget.

4How it looks on the exam

Exam-style question 1. At a status review, a project has a planned value of $80,000, an earned value of $88,000 and an actual cost of $96,000. How is the project performing?
A. Behind schedule and under budget
B. Ahead of schedule and over budget
C. Behind schedule and over budget
D. Ahead of schedule and under budget
Show the answer and the decode
Answer: B.
What it means
EV is above PV but below AC.
What is the question really asking?
Schedule and cost status.
Key words / trigger
“PV $80,000 · EV $88,000 · AC $96,000”
PMP logic
SV = 88 − 80 = +$8,000 (ahead). CV = 88 − 96 = −$8,000 (over budget). SPI 1.10, CPI 0.92. The PM should ask why: perhaps overtime is buying speed.
Why the wrong answer looks attractive
A: reverses both signs. C: correct on cost but wrong on schedule; EV > PV means ahead. D: correct on schedule but wrong on cost; AC > EV means over budget.

5Remember this

Your memory card

  • Spending alone says nothing: compare EV (work done) with PV (plan) and AC (cost)
  • PV = budgeted cost of work scheduled · EV = budgeted cost of work done · AC = actual cost
  • CV = EV − AC · SV = EV − PV: negative is bad
  • CPI = EV ÷ AC · SPI = EV ÷ PV: below 1.0 is bad
  • Measure EV with an agreed, objective method (0/100, 50/50, milestones, units); limit level of effort
  • SPI drifts to 1.0 at the end; earned schedule measures delay in time
  • EVM does not measure quality; a variance is a signal for root-cause analysis

📘 Quick reference: Study guide: Earned value formulas: CPI, SPI, EAC, ETC, VAC · Practice more PMP questions

The full lesson in the PMCLEAR app also has:
  • the rest of the lesson (The three basic measures, How earned value is measured, Variances: how far off are we?, Performance indexes: how efficient are we?, Reading the results in one sentence, Cumulative and period values, The weakness of SPI, and earned schedule, Earned value in agile and hybrid projects, Limits and good practice, Glossary, Sources and further reading)
  • a worked example
  • the common traps (wrong vs right)
  • 5 exam-style questions with the decode
  • a 3-question quick check
  • an interactive calculator
Open the full lesson → Create a free account

Sign up free and get 5 days of complimentary full access: exam simulations and 2,000 exam-level questions, clearly explained, also in your own language. Your progress stays saved.