EAC Formulas for the PMP Exam: Which Estimate at Completion Formula to Use

Estimate at completion (EAC) forecasts the total cost of the project. The exam gives you a clue in the question that tells you which EAC formula to use.

In simple words

EAC answers: if we continue like this, what will the whole project cost? The answer depends on the story. If the problem will continue, use the current efficiency (CPI). If the problem was a one-time event, the rest of the work costs what was planned. If the original estimate was wrong, estimate the rest again from the bottom up.

What the PMP exam wants

Current performance will continue (the most common): EAC = BAC ÷ CPI.

The variance was a one-time event and will not happen again: EAC = AC + (BAC − EV). The remaining work is done at the planned rate.

The original estimate is no longer valid: EAC = AC + bottom-up ETC (a new estimate for the remaining work).

Both cost and schedule problems will affect the rest (the question says so): EAC = AC + (BAC − EV) ÷ (CPI × SPI).

ETC = EAC − AC. VAC = BAC − EAC: a positive VAC means under budget at the end, negative means over budget. The rule “below 1 is bad” is for CPI and SPI, not for VAC. TCPI = (BAC − EV) ÷ (BAC − AC): above 1 means the remaining work must be done more efficiently than the work so far.

All EAC formulas in one table

Situation in the questionFormula
Current cost performance will continue (typical variance)EAC = BAC ÷ CPI
The variance was a one-time event (atypical)EAC = AC + (BAC − EV)
The original estimate is no longer validEAC = AC + bottom-up ETC
Both cost and schedule performance affect the remaining workEAC = AC + (BAC − EV) ÷ (CPI × SPI)
Cost of the remaining workETC = EAC − AC
Expected difference from the budget at the endVAC = BAC − EAC (positive = under budget)
Efficiency needed to finish within budgetTCPI = (BAC − EV) ÷ (BAC − AC) (above 1 = harder)

How to choose in three steps

1. Calculate CPI = EV ÷ AC (and SPI = EV ÷ PV if schedule is mentioned). 2. Find the clue in the story: will the problem continue, was it one-time, was the estimate wrong, or do cost and schedule both matter? 3. Use the matching formula from the table, then check the question: does it ask for EAC, ETC or VAC?

Real example

BAC = $100k, PV = $50k, EV = $40k, AC = $50k. CPI = 40 ÷ 50 = 0.8, SPI = 40 ÷ 50 = 0.8. Problem continues: EAC = 100 ÷ 0.8 = $125k (VAC = −$25k). One-time problem: EAC = 50 + 60 = $110k. Cost and schedule both: EAC = 50 + 60 ÷ 0.64 ≈ $143.8k. TCPI = 60 ÷ 50 = 1.2, so the team would need to be 20% more efficient to finish within the original budget.

The common trap

Tempting wrong answers: always using BAC ÷ CPI, or reading a negative VAC as good news. Look for the clue: “will continue”, “one-time”, “estimate was wrong”, “both cost and schedule”.

Remember: Continue → BAC÷CPI. One-time → AC+(BAC−EV). Estimate wrong → AC+new ETC. Both → AC+(BAC−EV)÷(CPI×SPI). VAC positive = good.

🗝 Words to notice in the question

“expected to continue”, “typical” → BAC÷CPI. “one-time”, “atypical”, “will not happen again” → AC+(BAC−EV). “original estimate was flawed” → bottom-up ETC. “schedule pressure also affects cost” → CPI×SPI

Try 2 practice questions

Choose an answer, or open “Show the answer.”

Question 1 BAC is $200k, EV is $80k and AC is $100k. A supplier problem caused the overrun, and it will not happen again. What is the EAC?

Show the answer

Answer: B. A one-time (atypical) variance: EAC = AC + (BAC − EV) = 100 + 120 = $220k. BAC ÷ CPI ($250k) would assume the problem continues.

Question 2 The forecast shows VAC = +$15k. What does this mean?

Show the answer

Answer: B. VAC = BAC − EAC. A positive VAC means the expected total cost is below the budget: under budget at the end.

Continue learning with PMCLEAR

The full chapter, with more questions like these, is part of PMCLEAR (88 chapters, 2,000 practice questions with explanations).

Create a free account → Practice more PMP questions

Creating an account is free. Full access is free for a limited time after you sign up; after that you can choose a paid plan. Your progress stays saved.

Already have an account? Log in · See the full chapter

Questions students ask

What is the EAC formula on the PMP exam?

There are four EAC formulas. The most common is EAC = BAC ÷ CPI, used when current cost performance is expected to continue. The others are AC + (BAC − EV) for a one-time variance, AC + bottom-up ETC when the original estimate is no longer valid, and AC + (BAC − EV) ÷ (CPI × SPI) when both cost and schedule performance will affect the remaining work.

What is the difference between EAC and ETC?

EAC (estimate at completion) is the expected total cost of the whole project. ETC (estimate to complete) is the expected cost of the remaining work only. ETC = EAC − AC.

Is a negative VAC good or bad?

Bad. VAC = BAC − EAC. A negative VAC means the project is expected to finish over budget; a positive VAC means under budget.

What does a TCPI above 1 mean?

TCPI = (BAC − EV) ÷ (BAC − AC). A value above 1 means the remaining work must be done more efficiently than the work so far to finish within the budget.